KOUFOS
v.
C. CZARNIKOW LIMITED
Lord Reid
Lord
Morris
of Borth-y-
Gest
Lord
Hodson
Lord Pearce
Lord
Upjohn
Lord Reid
my lords
By charter Party of 15th October, 1960 the Respondents chartered the
Appellant’s Vessel, Heron II, to proceed to Constanza, there to load a cargo
of 3,000 tons of sugar; and to carry it to Basrah, or, in the Charterer’s option,
to Jeddah. The vessel left Constanza on 1st November. The option was
not exercised and the vessel arrived at Basrah on 2nd December The Umpire
has found that ” a reasonably accurate prediction of the length of the voyage
” was twenty days “. But the vessel had in breach of contract made deviations
which caused a delay of nine days.
It was the intention of the Respondents to sell the sugar ” promptly after
” arrival at Basrah and after inspection by merchants “. The Appellant did
not know this but he was aware of the fact that there was a market for sugar
at Basrah. The sugar was in fact sold at Basrah in lots between 12th and 22nd
December but shortly before that time the market price had fallen partly by
reason of the arrival of another cargo of sugar. It was found by the Umpire
that if there had not been this delay of nine days the sugar would have fetched
£32 10s. Od. per ton. The actual price realised was only £31 2s. 9d. per ton.
The Respondents claim that they are entitled to recover the difference as
damage for breach of contract. The Appellant admits that he is liable to pay
interest for nine days on the value of the sugar and certain minor expenses but
denies that fall in market value can be taken into account in assessing damages
in this case.
McNair J., following the decision in The Parana L.R. 2 P.D. 118, decided
this question in favour of the Appellant. He said:
” In those circumstances it seems to me almost impossible to say that
” the shipowner must have known that the delay in prosecuting the
” voyage would probably result, or be likely to result, in this kind of loss.”
The Court of Appeal by a majority (Diplock and Salmon L.JJ., Sellers L.J.
dissenting) reversed the decision of the trial judge. The majority held that
The Parana laid down no general rule, and, applying the rule (or rules) in
Hadley and Another v. Baxendale and Others (1854) 9 Ex 341 as explained in
Victoria Laundry (Windsor) Ltd. v. Newman Industries Ltd. [1949] 2 K.B 528,
they held that the loss due to fall in market price was not too remote to be
recoverable as damages.
It may be well first to set out the knowledge and intention of the
parties at the time of making the contract so far as relevant or argued to be
relevant. The Charterers intended to sell the sugar in the market at Basrah
on arrival of the vessel. They could have changed their mind and exercised
their option to have the sugar delivered at Jeddah but they did not do so.
There is no finding that they had in mind any particular date as the likely date
of arrival at Basrah or that they had any knowledge or expectation that in late
November or December there would be a rising or a falling market. The
shipowner was given no information about these matters by the Charterers.
He did not know what the Charterers intended to do with the sugar. But
he knew there was a market in sugar at Basrah, and it appears to me that,
if he had thought about the matter, he must have realised that at least it
was not unlikely that the sugar would be sold in the market at market
price on arrival. And he must be held to have known that in any ordinary
market prices are apt to fluctuate from day to day: but he had no reason
to suppose it more probable that during the relevant period such fluctuation
2
would be downwards rather than upwards—it was an even chance that the
fluctuation would be downwards.
So the question for decision is whether a plaintiff can recover as damages
for breach of contract a loss of a kind which the defendant, when he made
the contract, ought to have realised was not unlikely to result from a breach
of contract causing delay in delivery. I use the words ” not unlikely ” as
denoting a degree of probability considerably less than an even chance but
nevertheless not very unusual and easily foreseeable.
For over a century everyone has agreed that remoteness of damage in
contract must be determined by applying the rule (or rules) laid down by a
Court including Lord Wensleydale (then Parke B.), Martin B and Alderson B.
in Hadley v. Baxendale. But many different interpretations of that rule
have been adopted by judges at different times. So I think that one ought
first to see just what was decided in that case, because it would seem wrong
to attribute to that rule a meaning which, if it had been adopted in that
case, would have resulted in a contrary decision of that case.
In Hadley v. Baxendale the owners of a flour mill at Gloucester which
was driven by a steam engine delivered to common carriers, Pickford & Co.,
a broken crank shaft to be sent to engineers in Greenwich. A delay of
five days in delivery there was held to be in breach of contract and the
question at issue was the proper measure of damages. In fact the shaft
was sent as a pattern for a new shaft and until it arrived the mill could
not operate. So the owners claimed £300 as loss of profit for the five
days by which resumption of work was delayed by this breach of contract.
But the carriers did not know that delay would cause loss of this kind.
Alderson B. delivering the judgment of the Court said (at page 355) :
” We find that the only circumstances here communicated by the
” plaintiffs to the defendants at the time the contract was made were
” that the article to be carried was the broken shaft of a mill, and that
” the plaintiffs were the millers of that mill. But how do these circum-
” stances show reasonably that the profits of the mill must be stopped
” by an unreasonable delay in the delivery of the broken shaft by the
” carrier to the third person? Suppose the plaintiffs had another shaft
” in their possession put up or putting up at the time, and that they
” only wished to send back the broken shaft to the engineer who made
” it; it is clear that this would be quite consistent with the above
” circumstances, and yet the unreasonable delay in the delivery would
” have no effect upon the intermediate profits of the mill. Or, again,
” suppose that at the time of the delivery to the carrier the machinery
” of the mill had been in other respects defective, then also the same
” results would follow.”
Then, having said that in fact the loss of profit was caused by the delay,
he continued:
” But it is obvious that in the great multitude of cases of millers
” sending off broken shafts to third persons by a carrier’ under ordinary
” circumstances, such consequences would not, in all probability, have
” occurred.”
Alderson B. clearly did not and could not mean that it was not reasonably
foreseeable that delay might stop the resumption of work in the mill. He
merely said that in the great multitude—which I take to mean the great
majority—of cases this would not happen. He was not distinguishing
between results which were foreseeable or unforeseeable, but between
results which were likely because they would happen in the great majority
of cases, and results which were unlikely because they would only happen
in a small minority of cases. He continued:
” It follows, therefore, that the loss of profits here cannot reasonably
” be considered such a consequence of the breach of contract as could
” have been fairly and reasonably contemplated by both the parties
” when they made this contract.”
He clearly meant that a result which will happen in the great majority of
cases should fairly and reasonably be regarded as having been in the
3
contemplation of the parties, but that a result which, though foreseeable
as a substantial possibility, would only happen in a small minority of cases
should not be regarded as having been in their contemplation. He was
referring to such a result when he continued:
” For such loss would neither have flowed naturally from the breach
” of this contract in the great multitude of such cases occurring under
” ordinary circumstances, nor were the special circumstances, which
” perhaps would have made it a reasonable and natural consequence
” of such breach of contract, communicated to or known by the
” defendants.”
I have dealt with the latter part of the judgment before coming to the
well known rule because the Court were there applying the rule and the
language which was used in the latter part appears to me to throw consider-
able light on the meaning which they must have attached to the rather vague
expressions used in the rule itself. The rule is that the damages ” should
” be such as may fairly and reasonably be considered either arising naturally,
” i.e. according to the usual course of things from such breach of contract
” itself, or such as may reasonably be supposed to have been in the con-
” templation of both parties at the time they made the contract as the
” probable result of the breach of it”.
I do not think that it was intended that there were to be two rules
or that two different standards or tests were to be applied. The last two
passages which I quoted from the end of the judgment applied to the facts
before the Court which did not include any special circumstances communica-
ted to the defendants ; and the line of reasoning there is that because in
the great majority of cases loss of profit would not in all probability have
occurred, it followed that this could not reasonably be considered as having
been fairly and reasonably contemplated by both the parties, for it would
not have flowed naturally from the breach in the great majority of cases.
I am satisfied that the Court did not intend that every type of damage
which was reasonably foreseeable by the parties when the contract was made
should either be considered as arising naturally i.e. in the usual course of
things or be supposed to have been in the contemplation of the parties.
Indeed the decision makes it clear that a type of damage which was plainly
foreseeable as a real possibility but which would only occur in a small minority
of cases cannot be regarded as arising in the usual course of things or be
supposed to have been in the contemplation of the parties: the parties are
not supposed to contemplate as grounds for the recovery of damage any
type of loss or damage which on the knowledge available to the defendant
would appear to him as only likely to occur in a small minority of cases.
In cases like Hadley v. Baxendale or the present case it is not enough that
in fact the plaintiff’s loss was directly caused by the defendant’s breach of
contract. It clearly was so caused in both. The crucial question is whether,
on the information available to the defendant when the contract was made,
he should, or the reasonable man in his position would, have realised that
such loss was sufficiently likely to result from the breach of contract to make
it proper to hold that the loss flowed naturally from the breach or that loss
of that kind should have been within his contemplation.
The modern rule in tort is quite different and it imposes a much wider
liability. The defendant will be liable for any type of damage which is
reasonably foreseeable as liable to happen even in the most unusual case,
unless the risk is so small that a reasonable man would in the whole circum-
stances feel justified in neglecting it. And there is good reason for the
difference. In contract, if one party wishes to protect himself against a
risk which to the other party would appear unusual, he can direct the other
party’s attention to it before the contract is made, and I need not stop to
consider in what circumstances the other party will then be held to have
accepted responsibility in that event. But in tort there is no opportunity
for the injured party to protect himself in that way, and the tortfeasor cannot
reasonably complain if he has to pay for some very unusual but nevertheless
4
foreseeable damage which results from his wrongdoing. I have no doubt
that to-day a tortfeasor would be held liable for a type of damage as unlikely
as was the stoppage of Hadley’s Mill for lack of a crankshaft: to anyone
with the knowledge the carrier had that may have seemed unlikely but the
chance of it happening would have been seen to be far from negligible. But
it does not at all follow that Hadley v. Baxendale would to-day be differently
decided.
As long ago as 1872 Willes J. said in Home v. Midland Railway Co. L.R.
7 C.P. 583 at page 590:
” The cases as to the measure of damages for a tort do not apply
” to a case of contract. That was suggested in a case in Bulstrode but
” the notion was corrected in Hadley v. Baxendale. The damages are
” to be limited to those that are the natural and ordinary consequences
” which may be supposed to have been in the contemplation of the
” parties at the time of making the contract.”
And in Cory v. Thames Ironworks L.R. 3 Q.B. 181 Blackburn J said (at
page 190):
” I think it all comes to this: the measure of damages when a party
” has not fulfilled his contract is what might be reasonably expected
” in the ordinary course of things to flow from the non-fulfilment of the
” contract, not more than that, but what might be reasonably expected
” to flow from the non-fulfilment of the contract in the ordinary state of
” things, and to be the natural consequences of it. The reason why the
” damages are confined to that is, I think, pretty obvious, viz. that
” if the damage were exceptional and unnatural damage, to be made
” liable for that would be hard upon the seller because if he had known
” what the consequences would be he would probably have stipulated for
” more time or, at all events, have used greater exertions if he knew
” that that extreme mischief would follow from the non-fulfilment of
” his contract.”
It is true that in some later cases opinions were expressed that the measure
of damages is the same in tort as it is in contract, but those were generally
cases where it was sought to limit damages due for a tort and not cases where
it was sought to extend damages due for breach of contract, and I do
not recollect any case in which such opinions were based on a full con-
sideration of the matter. In my view these opinions must now be regarded
as erroneous.
For a considerable time there was a tendency to set narrow limits to
awards of damages. Such phrases were used as that the damage was
not ” the immediate and necessary effect of the breach of contract” (per
Cockburn C.J. in Hobbs v. The London and South Western Railway Com-
pany L.R. 10 Q.B. 111 at page 118). The Parana was decided during that
period. But later a more liberal tendency can be seen. I do not think it
useful to review the authorities in detail but I do attach importance to what
was said in this House in R. & H. Hall, Ltd. v. W. H. Pim (Junior)
& Co. Ltd. (1928) 33 Com. Cas. 324.
In that case Pim sold a cargo of wheat to Hall but failed to deliver it.
Hall had resold the wheat but as a result of Pim’s breach of contract lost
the profit which they would have made on their sub-sale. Three of their
Lordships dealt with the case on the basis that the relevant question was
whether it ought to have been in the contemplation of the parties that a
resale was probable. The finding of the arbitrators was:
” The arbitrators are unable to find that it was in the contemplation
” of the parties or ought to have been in the contemplation of Messrs.
” Pim at that time that the cargo would be resold or was likely to be
” resold before delivery: in fact, the chances of its being resold as a
” cargo and of its being taken delivery of by Messrs. Hall were about
” equal.”
On that finding the Court of Appeal had decided in favour of Pim, saying
that, as the arbitrators had stated as a fact that the chances of the cargo
5
being resold or not being resold were equal, it was therefore “idle to
” speak of a likelihood or of a probability of a resale “.
Lord Dunedin pointed out that it was for the Court to decide what was
to be supposed to have been in the contemplation of the parties, and then
said:
” I do not think that ‘ probability’ . . . means that the chances
” are all in favour of the event happening. To make a thing probable
” it is enough, in my view, that there is an even chance of its happening.
” That is the criterion I apply; and in view of the facts, as I have said
” above, I think there was here in the contemplation of parties the
” probability of a resale.”
He did not have to consider how much less than a fifty per cent chance would
amount to a probability in this sense.
Lord Shaw went rather farther. He said:
” To what extent in a contract of goods for future delivery the
” extent of damages is in contemplation of parties is always extremely
” doubtful. The main business fact is that they are thinking of the
” contract being performed and not of its being not performed. But
” with regard to the latter if their contract shows that there were
” instances or stages which made ensuing losses or damage a not un-
” likely result of the breach of the contract, then all such results must
” be reckoned to be within not only the scope of the contract, but the
” contemplation of parties as to its breach.”
Lord Phillimore was less definite and perhaps went even farther. He
said that the sellers of the wheat knew that the buyers ” might well sell it
” over again and make a profit on the resale ” ; and that being so they ” must
” be taken to have consented to this state of things and thereby to have
” made themselves liable to pay ” the profit on a resale.
It may be that there was nothing very new in this but I think that Hall’s
case must be taken to have established that damages are not to be regarded
as too remote merely because, on the knowledge available to the defendant
when the contract was made, the chance of the occurrence of the event which
caused the damage would have appeared to him to be rather less than an
even chance. I would agree with Lord Shaw that it is generally sufficient
that that event would have appeared to the defendant as not unlikely to occur.
It is hardly ever possible in this matter to assess probabilities with any
degree of mathematical accuracy. But I do not find in that case or in cases
which preceded it any warrant for regarding as within the contemplation
of the parties any event which would not have appeared to the defendant,
had he thought about it, to have a very substantial degree of probability.
But then it has been said that the liability of defendants has been further
extended by Victoria Laundry (Windsor) Ltd. v. Newman Industries Ltd.
[1949] 2 K.B. 528. I do not think so. The plaintiffs bought a large boiler
from the defendants and the defendants were aware of the general nature of
the plaintiffs’ business and of the plaintiffs’ intention to put the boiler into
use as soon as possible. Delivery of the boiler was delayed in breach of
contract and the plaintiffs claimed as damages loss of profit caused by the
delay. A large part of the profits claimed would have resulted from some
specially lucrative contracts which the plaintiffs could have completed if
they had had the boiler: that was rightly disallowed because the defendants
had no knowledge of these contracts. But Asquith L. J. then said:
” It does not however follow that the plaintiffs are precluded from
” recovering some general (and perhaps conjectural) sum for loss of
” business in respect of dyeing contracts to be reasonably expected, any
” more than in respect of laundering contracts to be reasonably
” expected.”
It appears to me that this was well justified on the earlier authorities. It
was certainly not unlikely on the information which the defendants had
when making the contract that delay in delivering the boiler would result
in loss of business: indeed it would seem that that was more than an even
6
chance. And there was nothing new in holding that damages should be
estimated on a conjectural basis. This House had approved of that as early
as 1813 in Hall v. Ross 1 Dow. 201.
But what is said to create a ” landmark ” is the statement of principles
by Asquith L. J. on pages 539-40. This does to some extent go beyond the
older authorities and in so far as it does so, I do not agree with it. In
paragraph (2) it is said that the plaintiff is entitled to recover ” such part
” of the loss actually resulting as was at the time of the contract reasonably
” foreseeable as liable to result from the breach “. To bring in reasonable
foreseeability appears to me to be confusing measure of damages in contract
with measure of damages in tort. A great many extremely unlikely results
are reasonably foreseeable: it is true that Lord Asquith may have meant
foreseeable as a likely result, and if that is all he meant I would not object
farther than to say that I think that the phrase is liable to be misunder-
stood. For the same reason I would take exception to the phrase ” liable
” to result” in paragraph (5). Liable is a very vague word but I think that
one would usually say that when a person foresees a very improbable result
he foresees that it is liable to happen.
I agree with the first half of paragraph (6). For the best part of a century
it has not been required that the defendant could have foreseen that a breach
of contract must necessarily result in the loss which has occurred. But I cannot
agree with the second half of that paragraph. It has never been held to be
sufficient in contract that the loss was foreseeable as ” a serious possibility ”
or ” a real danger ” or as being ” on the cards “. It is on the cards that one can
win £100,000 or more for a stake of a few pence—several people have done
that. And anyone who backs a hundred to one chance regards a win as a
serious possibility—many people have won on such a chance. And the
Wagon Mound No. 2 [1966] 3 WLR 498 could not have been decided as it
was unless the extremely unlikely fire should have been foreseen by the ship’s
officer as a real danger. It appears to me that in the ordinary use of
language there is wide gulf between saying that some event is not unlikely or
quite likely to happen and saying merely that it is a serious possibility, a real
danger, or on the cards. Suppose one takes a well shuffled pack of cards, it
is quite likely or not unlikely that the top card will prove to be a diamond : the
odds are only 3 to 1 against. But most people would not say that it is quite
likely to be the nine of diamonds for the odds are then 51 to 1 against. On
the other hand I think that most people would say that there is a serious
possibility or a real danger of its being turned up first and of course it is on the
cards. If the tests of ” real danger ” or ” serious possibility ” are in future to
be authoritative then the Victoria Laundry case would indeed be a landmark
because it would mean that Hadley v. Baxendale would be differently decided
to-day. I certainly could not understand any Court deciding that, on the
information available to the carrier in that case, the stoppage of the mill was
neither a serious possibility nor a real danger. If those tests are to prevail in
future then let us cease to pay lip service to the rule in Hadley v. Baxendale.
But in my judgment to adopt these tests would extend liability for breach of
contract beyond what is reasonable or desirable. From the limited knowledge
which I have of commercial affairs I would not expect such an extension to be
welcomed by the business community and from the legal point of view I can
find little or nothing to recommend it.
Lord Asquith took the phrases ” real danger ” and ” serious possibility ”
from the speech of Lord du Parcq in Monarch Steamship Co., Ltd. v.
Karlshamns Oljefabriken (A/B) [1949] AC 196 so I must examine that case.
The facts were complicated but it is sufficient to say that a voyage was
prolonged by breach of contract so that war broke out before it was completed,
and by reason of an embargo imposed on the outbreak of war the cargo owner
had to incur great expense in transshipping his goods and having them carried
to the contract destination The contract was made in April 1939. The
question was whether he was entitled to recover this expense as damages for
the breach of contract and that depended on whether the outbreak of war and
7
consequent embargo were or ought to have been within the contemplation of
the contracting parties in April, 1939. By that time war was much more than
merely a serious possibility. Lord Porter said (at page 219): ” Accepting the
” view that the appellants ought to have foreseen the likelihood of war
” occurring …”. Lord Wright said (at page 222) ” There was indeed in 1939
” the general fear that there might be a war . . . . The possibility must have been
” in the minds of both parties “. Lord Uthwatt said (at page 232) that a
reasonable shipowner ” would regard the chance of war, not as a possibility
” of academic interest to the venture, but as furnishing matter which commer-
” daily ought to be taken into account”. And Lord Morton said (at page 235)
that the shipowner ” would feel that there was a grave risk of war breaking out
” in Europe “. On those assessments of the situation holding that the damage
which flowed from the outbreak of war was not too remote to be recoverable
was well within the existing law.
I do not think that Lord du Parcq intended to say that his view was
materially different. Indeed he quoted from Sir Winston Churchill ” No one
” who understood the situation could doubt that it meant in all human proba-
” bility a major war in which we should be involved “. So there was no need
for him to go farther than the existing law and I do not think that he intended
to do so. It is only by taking these two phrases out of their context that any
such intention could be inferred
It appears to me that, without relying in any way on the Victoria Laundry
case, and taking the principle that had already been established, the loss of
profit claimed in this case was not too remote to be recoverable as damages.
So it remains to consider whether the decision in The Parana established a rule
which, though now anomalous, should nevertheless still be followed. In that
case owing to the defective state of the ship’s engines a voyage which ought to
have taken 65 to 70 days took 127 days, and as a result a cargo of hemp fetched
a much smaller price than it would have done if there had been no breach of
contract. But the Court of Appeal held that the plaintiffs could not recover
this loss as damages. The vital part of their judgment is on page 123:
” In order that damages may be recovered, we must come to two
” conclusions—first, that it was reasonably certain that the goods would
” not be sold until they did arrive; and secondly, that it was reasonably
” certain that they would be sold immediately after they arrived, and that
” that was known to the carrier at the time when the bills of lading were
” signed.”
If that was the right test then the decision was right, and I think that that
test was in line with a number of cases decided before or about that time (1877).
But, as I have already said, so strict a test has long been obsolete. And, if one
substitutes for ” reasonably certain ” the words ” not unlikely” or some
similar words denoting a much smaller degree of probability, then the whole
argument in the judgment collapses. I need not consider whether there were
other facts which might be held to justify the decision, but I must say that
I do not see why the mere duration of the voyage should make much difference.
If The Parana had always been regarded as laying down a rule so that
carriage by sea was to be treated as different from carriage by land, one
would have to consider whether it would be proper to alter a rule which
had stood for nearly a century. But in Dunn v. Bucknall Brothers [1902]
2 K.B. 614 it was held that there was no general rule that damages could
not be recovered by loss of market on a voyage by sea, and for special
reasons such damages have been awarded in a number of later cases. So,
whether The Parana is formally overruled or not. it cannot be relied on as
establishing a rule so as to require the present case to be decided in a way
inconsistent with the general law as it exists to-day.
Some importance was attached in argument to Slater v. Hoyle & Smith,
Ltd. [1920] 2 K.B. 11 and the earlier cases there cited. Those cases deal
with sale of goods, and I do not think it necessary or desirable in the present
case to consider what the rule there is, whether it conflicts with the general
principles now established as to measure of damages, or whether, if it does
329304 A4
8
it ought or ought not to stand. Those are much too important questions
to be decided obiter in the present case, and I refrain from expressing any
opinion about them.
For the reasons which I have given I would dismiss this appeal.
Lord Morris of Borth-y-Gest
MY LORDS,
The Appellant (a shipowner) made a contract with the Respondents (as
Charterers) for the carriage of goods by sea. As a result of an admitted
breach of contract on the part of the shipowner the goods were delivered at
the port of destination several days later than they should have been delivered.
The Respondents as a result undoubtedly suffered financial loss. They had
intended to sell the goods as soon as the ship arrived at its destination.
They did sell the goods after the ship arrived but in the period of the delay
in arrival there was a fall in the market price. In consequence they suffered
loss in that they received less than they would have received if the Appellant
had not been in breach. They claimed to recover their loss as damages for
breach of contract.
The classic judgment in Hadley v. Baxendale (1854) 9 Ex 341 has con-
tinuously been recognised as enshrining and formulating the guiding rules
which are to be followed in deciding whether damage which has been the
result of a breach of contract should be paid for by the contract breaker.
The numerous reported decisions in the years since Hadley v. Baxendale was
decided show that sometimes there have been problems relating to the
meaning and intention of the words used in the judgment in that case and
that sometimes the problems have been those of ascertaining facts and then
of relating accepted principle to the facts as found. When consideration
has been given to the meaning and intention of the words used in the
judgment in Hadley v. Baxendale it has so often been manifest that words
which are but servants to convey and express meanings—cannot always be
servants of precision and may sometimes be given a dominance which is
above their status. If ” Language is the dress of thought”, it is the thought
that must be understood.
In the present case the problem is that of relating principle to ascertained
facts. The facts are carefully set out in the stated special case the clarity of
which earned the commendation of the learned judge. It is not necessary
to summarise them here. It will suffice to state that the Umpire found that
the Respondents were the shippers and were the owners of the cargo of
Hungarian sugar at shipment and at and after discharge. Had there been
no breach of contract the vessel would have arrived at Basrah some nine
days or so earlier than she did arrive. The time that would be taken in the
voyage from Constanza to Basrah could with reasonable accuracy be pre-
dicted to be twenty days. At the date of the charter party and at all times
thereafter it was the intention of the Respondents to sell the sugar cash
against delivery order promptly after arrival at Basrah and after inspection
by merchants. They did in fact do so. Immediately after discharge the
Respondents proceeded to permit inspection and to negotiate sales. Had
there been no deviation and consequently no breach of contract the selling
price of the sugar would have been one of £32 10s. 0d. per ton. The
average price realised after the late arrival of the sugar was £31 2s. 9d. per
ton. The fall in the market price was caused inter alia by the arrival on
schedule (between the date, i.e. the 22nd November, when the Appellant’s
ship should have arrived had it not deviated and the date, i.e. the 2nd
December, when it did arrive) of a ship carrying 8.000 tons of Formosan
sugar. The London price fell during November and the first half of
December. The Basrah prices do not conform to a set pattern but they
tend to decline during October and November to a low point in about
December. There was however no evidence that the decline in the London
and Basrah prices in November and the first half of December was caused by
9
any unusual or unpredictable factor. To these facts it may be added
that there was at all material times a market for sugar in Basrah. Sugar
was regularly bought and sold there in large quantities at prices which were
published. Some 200,000 tons were sold on the Basrah market in a year.
Prices would fluctuate considerably. The arrival of a steamer with a cargo
of sugar would affect the prices. The existence of the Basrah sugar market
was known to the Appellant at and before and after the date of the charter
party but the Appellant did not have detailed knowledge of the markets in
Basrah nor of those in London: the London daily price influences the Basrah
price though the latter is not directly related to the London price. The
carriage of sugar from the Black Sea to Iraqi ports including Basrah is a
recognised trade but a shipowner would ordinarily have no knowledge
whether a particular cargo has been or is to be sold prior to its arrival in
Iraq, or whether the sugar is being shipped in order that it should be sold
in the market on arrival. The Appellant had no actual knowledge (nor had
his brokers) that the Respondents intended to sell the sugar promptly after its
arrival at Basrah.
The famous rule in Hadley v. Baxendale postulates a contract which one
party has broken and relates to the ” damages which the other party ought to
” receive “. They are ” such as may fairly and reasonably be considered
” either arising naturally, i.e., according to the usual course of things, from
” such breach of contract itself, or such as may reasonably be supposed
” to have been in the contemplation of both parties, at the time they made
” the contract, as the probable result of the breach of it”. The judgment
proceeds to give illustrative guidance. Thus a contract may be one actually
made under special circumstances. If they were ” communicated by the
” plaintiffs to the defendants, and thus known to both parties, the damages
” resulting from the breach of such a contract, which they would reasonably
” contemplate, would be the amount of injury which would ordinarily follow
” from a breach of contract under these special circumstances so known and
” communicated “. If however such special circumstances were wholly
unknown to the contract breaker then he ” at the most could only be
” supposed to have had in his contemplation the amount of injury which
” would arise generally, and in the great multitude of cases not affected by
” any special circumstances from such a breach of contract “. The judgment
proceeds to point out that if special circumstances have been known, then
the parties could have been provided by special terms as to the damages to be
payable in the event of a breach: it would be unjust to deprive them of the
advantage of so providing.
In the present case there was no special communication of special cir-
cumstances by reference to which the contract of carriage was made. The
problem presented was therefore whether with the knowledge possessed by
the parties at the time when the contract was made the loss in fact suffered
by the Respondents due to the delayed arrival (in breach of contract) of
the sugar could fairly and reasonably be considered as arising naturally (i.e.
according to the usual course of things) from such breach. When parties
enter into a contract they do not ordinarily at such time seek to work out
or to calculate the exact consequences of a breach of their contract. On the
facts of the present case it is however pertinent to pose the enquiry as to
what the natural ordinary and sensible answer of the Appellant would have
been if he had asked himself what the result for the Respondents would be
if he (the Appellant) in breach of contract and therefore unjustifiably caused
his ship to arrive at Basrah some nine or ten days later than it could and
should have arrived. While the Appellant did not know precisely what plans
the Respondents had made he could be reasonably sure of one thing, namely
that they had contracted for the Appellant’s ship to proceed at all convenient
speed to its destination because they wanted to have their cargo delivered
at its destination at such time as the ship could be expected to arrive. The
Appellant knew when the charter party was made (on the 15th October,
1960) that if the vessel arrived for loading at Constanza (it had been con-
fidently expected that she would arrive, as she in fact did, on the 27th
October) and if the Respondents did not (not later than five days prior to
10
the commencement of loading) declare that they exercised the option of
discharging the cargo at Jeddah then there was the obligation after loading
the cargo to proceed with all convenient speed to Basrah. The Appellant
could and should at the very least have contemplated that if his ship was
nine days later in arriving than it could and should have arrived some
financial loss to the Respondents or to an endorsee of the bill of lading
might result. I use the words ” at the very least” and the word ” might”
at this stage so as to point to the problem which is highlighted in this case.
It is here that words and phrases begin to crowd in and to compete. Must
the loss of the Respondents be such that the Appellant could see that it was
certain to result? Or would it suffice if the loss was probable or was likely
to result or was liable to result? In the present context what do these words
denote? If there must be selection as between them which one is to be
employed to convey the intended meaning?
I think that it is clear that the loss need not be such that the contract
breaker could see that it was certain to result. The question that arises
concerns the measure of prevision which should fairly and reasonably be
ascribed to him.
My Lords, in applying the guidance given in Hadley v. Baxendale I would
hope that no undue emphasis would be placed upon any one word or phrase.
If a party has suffered some special and peculiar loss in reference to some
particular arrangements of his which were unknown to the other party and
were not communicated to the other party and were not therefore in the
contemplation of the parties at the time when they made their contract, then
it would be unfair and unreasonable to charge the contract-breaker with
such special and peculiar loss. If, however, there are no ” special and extra-
” ordinary circumstances beyond the reasonable prevision of the parties ”
(see the speech of Lord Wright in Monarch Steamship Co., Ltd. v. Karlshamns
Oljefabriker (AB) [1949] AC 196, 221) then it becomes very largely a
question of fact as to whether in any particular case a loss can ” fairly and
” reasonably” be considered as arising in the normal course of things.
Though in these days commercial cases are not tried with juries, in his speech
in the Monarch Steamship case (supra) Lord du Parcq pointed out that in
the end what has to be decided is a question of fact and therefore a question
proper for a jury and he added: —
” Circumstances are so infinitely various that, however carefully general
” rules are framed, they must be construed with some liberality and not
” too rigidly applied. It was necessary to lay down principles lest juries
” should be persuaded to do injustice by imposing an undue, or perhaps
” an inadequate, liability on a defendant. The Court must be careful,
” however, to see that the principles laid down are never so narrowly
” interpreted as to prevent a jury, or judge of fact, from doing justice
” between the parties. So to use them would be to misuse them.”
If this approach is followed then I doubt whether the necessity arises to
express a preference or any definite preference as between words and phrases
that were submitted for your Lordships’ consideration. The result in any
particular case need not depend upon giving pride of place to any one of
such phrases as ” liable to result” or ” likely to result” or ” not unlikely to
” result”. Each one of these phrases may be of help but so may many others.
In Smeed v. Foord in 1859, 1 El. & El. 602, Compton, J. referred in his
judgment (at page 616) to the doctrine of Hadley v. Baxendale, and said:
” The second branch of the rule there laid down appears to me to come
” to much the same thing as the first: for damages which may reasonably
” be supposed to have been contemplated by the contracting parties, are
” damages which naturally arise from a breach of the contract. I doubt
” whether, in these cases, it is the duty of a Judge to lay down more to
” the jury than that the plaintiff is entitled to such damages as are the
” natural consequences of the breach of contract. The question what
” are such natural consequences is, I think, in each case, rather for the
11
” jury than for the Judge; just as it is for them, not for him, to assess
” the amount of damages.”
Somewhat comparable language was used in 1868 by Bovill, C.J., in his
judgment in British Columbia Saw-Mill Co. v. Nettleship, L.R. 3 C.P. 490,
when (at page 505) he said:
” The extent of carrier’s liability is to be governed by the contract he
” has entered into, and the obligations which the law imposes upon him.
” He is not to be made liable for damages beyond what may fairly be
” presumed to have been contemplated by the parties at the time of
” entering into the contract. It must be something which could have been
” foreseen and reasonably expected, and to which he has assented
” expressly or impliedly by entering into the contract.”
In his speech in the Monarch Steamship case (supra) Lord Porter refers
(at page 214) to what ” could reasonably have been foreseen ” and to what
” a shipowner ought to have foreseen ” as ” likely to occur “. At page 215
he spoke of what a shipowner ” ought reasonably to have contemplated “.
Lord Wright in the same case (at page 221) refers to cases where ” it would
” not be fair or reasonable to hold the defendant responsible for losses which
” he could not be taken to contemplate as likely to result from his breach of
” contract”. Lord Wright pointed out that the Court will assume that the
parties, as business men, will have all reasonable acquaintance with the
ordinary course of business, and he spoke (see page 224) of what ” reasonable
” business men must be taken to have contemplated as the natural or probable
” result if the contract was broken “. Lord Uthwatt in his speech referred to
what a reasonable shipowner ought reasonably to have foreseen: he would
in the circumstances of that case have regarded the chance of war ” not as
” a possibility of academic interest to the venture, but as furnishing matter
” which commercially ought to be taken into account “. Lord du Parcq said
at page 233:
” Damage arises ‘ according to the usual course of things’ if, in the
” circumstances existing at the date of the contract, both parties to it,
” supposing them to have considered the probable effects of a breach of
” the contract, with due regard to events which might reasonably be
” expected to occur, must be assumed as reasonable men to have foreseen
” such damage as at least a serious possibility.”
Furthermore, in reference to the facts in that case, Lord du Parcq (at
page 233) said:
” In order that the Respondents might succeed in establishing their
” case, it was not necessary, in my opinion, that the parties to the contract
” should be shown to have contemplated the outbreak of war as something
” certain and unavoidable. They are not to be supposed to have had
” the gift of prophecy. It is enough if they may reasonably be assumed
” to have contemplated a war, and the likelihood that it would lead
” to such an embargo as was in fact imposed, as a real danger which
” must be taken into account.”
My Lords, the words phrases and passages to which I have referred
are useful and helpful indications of the application of the rule in Hadley v.
Baxendale. But they neither add to the rule nor do they modify it. I regard
the illuminating judgment of the Court of Appeal in Victoria Laundry
(Windsor) Ltd. v. Newman Industries Ltd. [1949] 2 K.B. 528 as a most
valuable analysis of the rule. It was there pointed out (at page 540) that
in order to make a contract-breaker liable under what was called “either
” rule ” in Hadley v. Baxendale it is not necessary that he should actually
have asked himself what loss is liable to result from a breach but that
it suffices that if he had considered the question he would as a reasonable
man have concluded that the loss in question was liable to result. Nor
need it be proved, in order to recover a particular loss, that upon a given
state of knowledge he could, as a reasonable man, foresee that a breach
must necessarily result in that loss. Certain illustrative phrases are employed
in that case. They are valuable by way of exposition but for my part I
12
doubt whether the phrase ” on the cards ” has a sufficiently clear meaning
or possesses such a comparable shade of meaning as to qualify it to take its
place with the various other phrases which line up as expositions of the rule.
If the problem in the present case is that of relating accepted principle
to the facts which have been found, I entertain no doubt that if at the time
of their contract the parties had considered what the consequence would be
if the arrival of the ship at Basrah was delayed they would have contemplated
that some loss to the Respondents was likely or was liable to result. The
Appellant at the time that he made his contract must have known that if
in breach of contract his ship did not arrive at Basrah when it ought to
arrive he would be liable to pay damages. He would not know that a loss
to the Respondents was certain or inevitable but he must, as a reasonable
business man, have contemplated that the Respondents would very likely
suffer loss, and that it would be or would be likely to be a loss referable
to market price fluctuations at Basrah. I cannot think that he should escape
liability by saying that he would only be aware of a possibility of loss but
not of a probability or certainty of it. He might have used any one of many
phrases. He might have said that a loss would be likely: or that a loss
would not be unlikely: or that a loss was liable to result: or that the risk
that delay would cause loss to the Respondents was a serious possibility:
or that there would be a real danger of a loss: or that the risk of his being
liable to have to pay for the loss was one that he ought commercially to
take into account. As a practical business man he would not have paused
to reflect on the possible nuances of meaning of any one of these phrases.
Nor would he have sent for a dictionary.
The carriage of sugar from the Black Sea to Iraqui ports (including Basrah)
is a recognised trade. The Appellant knew that there was a sugar market at
Basrah. When he contracted with the Respondents to carry their sugar to
Basrah, though he did not know what were the actual plans of the
Respondent, he had all the information to enable him to appreciate that a
delay in arrival might in the ordinary course of things result in their suffering
some loss. He must have known that the price in a market may fluctuate.
He must have known that if a price goes down someone whose goods are
late in arrival may be caused loss.
Since in awarding damages the aim is to award a sum which as nearly
as possible will put the injured party into the position in which he would
have been if the breach of contract had not caused him loss and if in all
the circumstances he had acted reasonably in an effort to mitigate his loss,
I think that it must follow that, where there is delay in arrival, in many
cases the actual loss suffered (above the amount of which there ought not
to be recovery) can be measured by comparing the market price of the goods
at the date when they should have arrived and the market price when they
did arrive. That prima facie is the measure of the damages.
I can see no fault, therefore, in the assessment of the damages in the
present case unless there is some rule of law that in the case of carriage of
goods by sea damages for delay in arrival will ordinarily be limited to
interest on the value of goods over the period of their delay. It is said
that such a rule underlies the decision in The Parana L.R. 2 P.D. 118. In
reference to the suggestion that there is a special rule limiting damages for
delay in delivery in the case of carriage of goods by sea Lord Porter in
his speech in the Monarch Steamship case (supra) said at page 219:
” No doubt expressions of opinions to that effect are to be found,
” perhaps more frequently in the days of sailing ships when prolonged
” delay was to be expected, but it never was a rule of law—merely a
” working practice answering to the circumstances of the time and subject
” to the consideration that the contract must be reasonably performed.”
The Parana (which was decided in 1877) was a case in which, owing to the
weakness and defective state of her engines, a ship took 127 days on a
voyage from Manilla and Ilo-Ilo to London for which a period of 65 or
70 days was said to be a fair average time. As a result an assignee of bills of
lading of certain goods on the ship claimed to recover damages resulting
13
from unreasonable delay in the carriage of goods. The owner of the ship
admitted liability and what was in issue was the amount of the damages.
As to one portion of the cargo damages were given for a deterioration in
quality due to delay. As to another portion of the cargo the claim was
for the difference between the market price at the time when the goods
arrived and at the time when they ought to have arrived. As to that part
of the claim the Registrar, who was directed to report upon the amount of
damages, considered that the Court should refuse to entertain any claim
for loss of market in such cases. In his report (see The Parana L.R. 1 P.D.
452) he said that the practice of the Court of Admiralty should be followed
which was merely to allow a sum representing loss of interest for the period
of delay on the capital value of the cargo. One reason given was that the
loss of market “could not by any possibility have been within the con-
” temptation of the parties ” when the cargo was put on board at Manilla.
He appeared to think that a fall in the price of the goods could not have
been in the contemplation of the parties when the contract was made because
for aught they knew the price might have risen.
On appeal, in objection to the report of the Registrar, it was held by Sir
Robert Phillimore that the registrar ought to have included in the damages
the difference between the market price of the cargo at the time when it was
delivered and at the time when it ought to have been delivered. He said
at page 464): —
” Why should not the ascertained difference between the market price
” when the goods might have been sold, had there been no delay, and
” the market price which they would fetch after the delay, be a reason-
” able measure of the loss of the merchant’s profits? The depreciation is
” the direct consequence of the carrier’s default; in other words, he
” must be taken to have known or contemplated that the merchant desired
” a safe and a quick transport of his marketable goods to their intended
” market.”
On appeal to the Court of Appeal L.R. 2 P.D. 118 the judgment was
reversed though the principle was accepted that if circumstances are known
to the carrier from which the object of the sender ought in reason to be
inferred so that the object may be taken to have been within the contempla-
tion of both parties damages may be recovered for the natural consequences
of the failure of that object. Mellish LJ. in his judgment pointed to differ-
ences between cases where there was delay by carriers on land and cases
of ” carriage of goods for a long distance by sea “. , My Lords, I confess
that the differences do not seem to me to be differences in principle. Mellish
L.J. considered that there was an uncertainty as to whether the plaintiff was
affected by the delay in arrival of the goods Pointing to the circumstance
that the Plaintiff did not sell the goods on arrival Mellish L.J. considered
that he might have acted in the same way if the goods had arrived in time
—with the result that the delay did not affect the plaintiff and to give him
damages would be to give him speculative damages. So far as principle is
concerned I prefer the judgment of Sir Robert Phillimore. It is to be
remembered however that Mellish L.J. accepted as applicable to carriage
of goods by sea both the language used in Simpson v. London & North
Western Railway Co. 1 Q.B.D. 274, 277 (as cited by Sir Robert Phillimore)
and also the language of the Lord Chief Baron in Home v. Midland Railway
Co. L.R. 8 C.P. 131 at page 137 The language used by the Lord Chief
Baron in Horne’s case was the language of Hadley v. Baxendale. In prin-
ciple it seems to me that the rule in Hadley v. Baxendale must in these days
be applied in cases of carriage by goods by sea. If the parties for some
particular reason have contracted on the basis that there is no obligation to
proceed normally to a destination then delay would not constitute a breach.
If, however, there is delay which amounts to a breach of contract I see no
reason for adopting some special formula in the assessment of damages (such
as giving interest on the capital value of the goods carried) or for any artificial
divergence from the principles that govern the assessment of damages.
14
In The Notting Hill L.R. 9 P.D. 105 which was decided in 1884, Hannen J.
expressed disagreement with the decision in The Parana but reluctantly
felt that he was bound by it. The Court of Appeal agreed that it was an
authority binding on them Brett M.R. did not wish to say that, had it
been for him to decide the case, he would have decided it differently.
In Dunn v. Bucknall Brothers [1902] 2 K.B. 614 it was known to the
Defendants that the reason why the plaintiffs had shipped goods (on the ship
of which the defendants were charterers) for carriage to Algoa Bay was so
that the goods should be supplied to British troops in South Africa and the
defendants knew that the goods would sell at a much higher price if delivered
in due course than if delivered at a later time when a large importation of
similar goods would force prices down. For a breach of duty which resulted
in the delayed arrival of the goods the defendants were held liable in damages.
It was contended in the Court of Appeal that damages for loss of market
are not recoverable in the case of delay in carriage by sea and that a shipper
is only entitled to interest on the value of the goods from the date when they
should have been delivered down to the date of actual delivery. The con-
tention was held to be ill-founded and Collins M.R. giving the judgment of
the Court consisting of himself, Stirling L.J. and Cozens-Hardy L.J. said that
they did not understand The Parana (supra) as establishing any such general
proposition as that damages could not be recovered for loss of market on a
voyage by sea. He said:
” There can be no absolute peremptory rule taking voyages by sea
” out of the principles which regulate the measure of damages on
” breach of other contracts. It is only because the possible length of
” voyages and the consequent uncertainty as to the times of arrival
” may in many cases eliminate the supposition of any reasonable
” expectation as to the state of the market at the time of arrival that
” as a general rule damages for loss of market by late delivery are not
” recoverable from the carrier by sea. It is certainly not a rule of
” law, it is only an inference of fact, that from the circumstances of
” the case no reasonable assumption as to the state of the market
” at the time of arrival could have been a factor in the contract
” between the parties.”
He proceeded to point out that as the means of sea transit improved then
voyages of three or four weeks duration could be accomplished with
almost absolute certainty and furthermore that the state of the market
at such reasonably calculated date of arrival could well be ” a vital factor
” present to the minds of both parties at the time of making the contract”.
He then added:
” Wherever the circumstances admit of calculations as to the time
” of arrival and the probable fluctuations of the market being made with
” the same degree of reasonable certainty in the case of a sea as
” of a land transit, there can be no reason why damages for late delivery
” should not be calculated according to the same principles in both
” cases.”
On the facts of that case it was known to the defendants that the goods
would sell at a much higher price if duly delivered than if tardily delivered
and the words I have quoted were uttered in that context. I do not consider
however that where in breach of contract there is delay in delivery, damages
will only be recoverable if there can be a calculation in advance of the
precise financial consequences that delay will cause. If there can be such
a calculation then the carrier would know at the time of his contract of
carriage exactly what the effect would be if by delaying delivery he broke
his contract. But I cannot think that he should be partially exonerated
merely by the circumstance that he could not calculate in advance the extent
of the damage that he would cause if he broke his contract. With the
knowledge possessed by the Appellant in the present case, if. at the time
of the contract, he had considered what the consequences would be if. in
breach of contract, he delayed the delivery of the goods he was carrying,
15
he must at least have contemplated that there might well be market fluctua-
tions as between the due date of delivery and the actual date of delivery.
If by the actual date of delivery the market price had advanced he might
be freed of any serious liability. But he must have contemplated that
if the market went the other way he would be causing loss. In running
the risk of causing that loss it would not be reasonable to exonerate him
merely because in advance the measure of the loss could not be calculated.
In R. & H. Hall Limited v. W. H. Pim (Junior) & Co. Ltd. 33 Com.
Cas. 324 there was a failure by sellers to deliver goods to buyers: there
had been a sub-sale by the buyers and then a further sub-sale. The buyers
were held entitled to recover both their loss of profit and also to recover
the damages that they would have to pay to their sub-purchaser. It was
a case where the parties had actually provided for the very case of sub-
sales. Non-performance of the contract would therefore be known before-
hand by both parties to be non-performance of a contract in which inter-
mediate sales might take place. A question was raised as to whether the
parties would have considered all the damage to be probable. Lord
Shaw of Dunfermline said:
” To what extent in a contract of goods for future delivery the
” extent of damages is in contemplation of parties is always extremely
” doubtful. The main business fact is that they are thinking of the
” contract being performed and not of its being not performed. But
” with regard to the latter if their contract shows that there were
” instances or stages which made ensuing losses or damage a not
” unlikely result of the breach of the contract, then all such results
” must be reckoned to be within not only the scope of the contract,
” but the contemplation of parties as to its breach.”
Further Lord Shaw said that he did not think—
” that in such a contract people come to contemplate with any
” exactitude the particular probable results which would follow from
” a breach; say, that there would be a probable chance of re-selling
” at a profit or that the chance of that would be even with their not
” selling at a profit. What the parties to a contract such as this do
” is not to estimate that the chances will be one way or the other or
” will have this amount of probability or the other, but simply to
” contemplate that trade chances are not unlikely to occur, and to make
” a contract to cover such chances if any.”
In the same case Lord Phillimore referred to damages ” which naturally
” flow ” from a breach of contract and to damages which ” the law super-
” adds in appropriate cases ” being ” those damages which, though they
” do not always or even usually flow from the breach of contract, are, at
” the time of making the contract, recognised by the parties as those which
” in a particular case may result from a breach “. He added:
” These are called damages in the contemplation of the parties, not
” because the parties contemplate a breach of contract, but because
” they recognise that a breach is possible, and they reckon that these
” damages may flow from that breach. I designedly use the word
” ‘ may’. There may be cases where the word to be used might be
” ‘ will’, but there are also cases and more common cases where the
” word to use is ‘ may ‘.”
Though that case was one in which the parties had made express pro-
visions in regard to sub-sales with the result that they must have ” recog-
” nised ” that a purchaser might have to pay damages to his sub-purchaser
if the vendor failed to deliver, the expressions used in the speeches
illustrate that damages could be recoverable in respect of a loss which
might occur or which the parties could contemplate as not unlikely to
occur. The present case is one in which no special information was given
to the carrier as to what the Respondents intended to do with the goods
after they arrived at Basrah. In those circumstances in deciding what
damages would fairly and reasonably be regarded as arising if the delivery
-
- 8
16
of the goods was delayed I think that the reasonable contemplation of a
reasonable shipowner at the time of the making of the charter party must
be considered. I think that such a shipowner must reasonably have con-
templated that if he delivered the sugar at Basrah some nine or ten days
later than he could and should have delivered it then a loss by reason of
a fall in the market price of sugar at Basrah was one that was liable
to result or at least was not unlikely to result. This results from the facts
of this case. It is a question of what the parties contemplated. Even without
notice of special circumstances or special considerations there may be
situations where it is plain that there was a common contemplation. In his
dissenting judgment in The Arpad [1934] P. 189 Scrutton L.J. (at page 203)
said:
” I am inclined to think that in contracts of carriage from wheat-
” producing districts, it is always so probable that the shipper is sending
” for resale, or for sale to a person who will resell, that the carrier will
” be liable if there is no market, for the effect on a contract of sale of
” his conversion or unjustifiable failure to deliver.”
Whether this be so or not the Appellant in the present case must at least have
appreciated that the Respondents wanted to have the goods at Basrah at the
date when they should have been delivered there. What could clearly be
foreseen was that the Respondents would be without their goods at the place
where, and on the date when, they were entitled to expect to have them.
Had there not been delivery at all the damages would have been measured
by relation to the market price of the goods at the date when they should
have been delivered. In such an eventuality the Respondents would have
been entitled to acquire goods to replace those which, either by reason of
their having been lost or for some other reason, were not delivered. By a
parity of reasoning since the parties had not contracted on the basis that
the Appellant could deliver as and when he liked but on the basis that he
should proceed at all convenient speed and so should deliver on the date
that could with reasonable accuracy be predicted, the Respondents would be
entitled, if it were necessary, to acquire goods to replace those which had
not arrived. If when the goods later arrived the market price had advanced
the Respondents would suffer no loss: if the market price had declined they
would suffer loss. If they actually suffered loss it would prima facie be
measured as the difference between the market price at the date when the
goods should have been delivered and the market price at the date when
they were delivered.
I would dismiss the appeal.
Lord Hodson
MY LORDS,
The broad question which arises on the appeal is what is the correct
measure of damages for wrongful delay by a shipowner in the performance
of a contract for the carriage of goods by sea.
The Respondents contend that the ordinary measure of damages for delay
in delivery of goods for which there is a market is the difference between
the market value of the goods at their destination on the date when they
arrive, and the value at the date when they should have arrived if there
had been no breach of contract. The loss so measured is one which arises
naturally according to the usual course of things. This right to recover does
not depend on any special knowledge of the party in breach. It applies to
contracts of carriage by sea and by land in all ordinary cases.
The Appellant contends, on the other hand, that except in special circum-
stances, which are not to be found in this case, the measure of damages
is limited to the interest on the value of the goods during the period of delay.
In these circumstances the Appellant admitted liability for £172 consisting
of £12 10s. Od. (cable expenses) and £159 9s. 6d. (interest at 6 per cent, per
17
annum on the full value of the cargo during the period of the delay) upon
the facts found and stated in the Special Case.
The Umpire awarded the charterers, in addition to the above sum of £172,
£4010 16s. 8d. in respect of the fall in value of the goods during the delay.
McNair J. on questions of law being submitted for the decision of the Court
as to (inter alia) the correct measure of damages held that the Umpire was
wrong in law and that the Respondents were entitled only to the admitted
sum of £172, made up in the main of interest charges.
The Court of Appeal, Diplock and Salmon, LJJ. (Sellers LJ. dissenting)
restored the Umpire’s award.
The ultimate question for decision is whether, as a matter of law, contracts
for the carriage of goods by sea are in a special class, having regard to the
intrinsic differences there are between such contracts and contracts for the
carriage of goods by land. For example, in the former class, it is pointed
out that goods may be sold before shipment or during the voyage or intended
for the purposes of stocking or consumption at the port of destination and
that the contemplation of the parties that the goods may be resold by the
charterer at the port of destination is not necessarily to be inferred. In
addition it is urged that ocean voyages are liable to be affected by weather,
by congestion at loading and discharging ports and similar factors which
account for a different treatment being given to cases of carriage of goods
by sea.
There is on the face of it no reason why the charterer should not be
entitled to the value of that of which he has been deprived by the breach of
contract independently of his intention to sell again and sale during the
voyage or before the shipment is in any case irrelevant since the purchaser
would stand in the charterer’s shoes. There is nothing speculative about the
claim and what the charterer does with the goods should not make any
difference. This should apply to contracts of carriage by land or sea.
Consideration of sea and weather conditions has been thought to be the
basis of the decision in The Parana (1877) 2 P.D. 118. This appears from
the judgment of Sir Richard Henn Collins M.R. in Dunn and Others v.
Bucknall Brothers [1902] 2 K.B. 614. The uncertainties of The Parana’s
voyage were so great, said the Master of the Rolls in Dunn v. Bucknall, that
the parties could not be said to have contracted on the footing that the goods
would arrive at any particular moment. The headnote to Dunn v. Bucknall,
however, concisely states as a summary of the judgment that there is no rule
of law that damages cannot be recovered for loss of market on a contract
of carriage by sea. This, I think, was really accepted by the Appellant
and also in the main by McNair J. although Sellers L.J. went so far as to
say that it was desirable in establishing a basis for damages to avoid
fortuitous elements unless the parties have already contracted that the
chance change of market price should fall on the shipowner if it happened
to be less and not equal to or more than the price which could have been
obtained without a breach of contract.
That was in substance the position taken up by the Appellant before
your Lordships. He accepted the established authority of the judgment in
Hadley v. Baxendale (1854) 9 Ex 341. The case concerned a broken crank
shaft delivered to common carriers to be sent to engineers for repair. There
was a delay of five days in delivery and the issue was as to the measure of
damages for breach of contract. In the judgment of the Court, which
consisted of Barons Parke, Martin and Alderson, at page 354 it was said:
” We think the proper rule in such a case as the present is this:
” Where two parties have made a contract which one of them has broken,
” the damages which the other party ought to receive in respect of such
” breach of contract should be such as may fairly and reasonably be
” considered either arising naturally, i.e., according to the usual course
” of things, from such breach of contract itself, or such as may be
” reasonably be supposed to be in the contemplation of both parties, at
18
” the time they made the contract, as the probable result of the breach
” of it.”
The phrases beginning “either” and “or” are commonly said to divide
the rule laid down by the Court into two parts, the one arising ” according
” to the usual course of things ” and the other relating to special circumstances
in which the contract was made.
The Appellant argued that the fluctuations of market due to unforeseen
and unpredictable causes during the period of delay is not of itself ” according
” to the usual course of things”. He argued that there were no facts here
to bring the second part of the rule into operation, and in this I agree with
him, for no special notice was given. Hence he said that damages for loss
of market are not recoverable and that these damages could only be
recovered in special cases covered by the second part of the rule.
The word ” probable ” in Hadley v. Baxendale covers both parts of the
rule and it is of vital importance in applying the rule to consider what the
court meant by using this word in its context. The common use of this word
is no doubt to imply that something is more likely to happen than not. In
conversation, if one says to another.” If you go out in this weather you will
” probably catch a cold ” this is, I think, equivalent to saying that you believe
there is an odds on chance that the other will catch a cold.
The word ” probable” need not, however, bear this narrow meaning.
In R. & H. Hall Limited v. W. H. Pim (Junior) & Company Limited (1928)
33 Com. Cas. 324, Lord Dunedin, after stating his belief in a general
agreement that the law as to calculation of damages, due under breach of a
contract, was settled by the case of Hadley v. Baxendale, said that the
difficulty lies in the application to the facts of each case.
The instant case furnishes an example of this difficulty. Assistance is to
be gained from some of the expressions used in Hall v. Pim which concerned
a loss of profit on resale. On failure by sellers to deliver goods to buyers,
the buyers were held entitled to recover the damages they would have to pay
to a sub-purchaser. Lord Dunedin thought it was enough that there was an
even chance of a resale happening. Lord Shaw thought it not unlikely that
a resale would take place and Lord Phillimore that the parties contemplated
that a resale may take place.
In the Monarch Steamship Co, Ltd. v. Karlshamns Oljefabriker (AB) 1949
A.C. 196 Lord Du Parcq used in applying the first part of the rule in Hadley
v. Baxendale the words ” serious possibility ” and ” real danger ” while Lord
Morton of Henryton spoke of ” grave risk “.
A close study of the rule was made by the Court of Appeal in the case
of the Victoria Laundry (Windsor) Ltd. v. Newman Industries Ltd.; Coulson
& Co. Ltd. (Third Parties) [1949] 2 K.B. 528. The judgment of the Court,
consisting of Tucker, Asquith and Singleton, L.JJ., was delivered by
Asquith L.J., who referred to the Monarch Steamship case (supra) and
suggested the phrase ” liable to result” as appropriate to describe the degree
of probability required. This may be a colourless expression but I do not find
it possible to improve on it. If the word ” likelihood ” is used it may convey
the impression that the chances are all in favour of the thing happening, an
idea which I would reject.
I find guidance in the use of the expression ” in the great multitude of
cases” which is to be found in more than one place in the judgment in
Hadley v. Baxendale and indicates that the damages recoverable for breach
of contract are such as flow naturally in most cases from the breach, whether
under ordinary circumstances or from special circumstances due to the
knowledge either in the possession of or communicated to the defendants.
This expression throws light on the whole field of damages for breach of
contract and points to a different approach from that taken in tort cases.
True that where the facts are the same in two cases the damages will no
doubt be the same whether the claim is made in contract or in tort; compare
The Notting Hill (1884) 9 P.D. 105 where although the claim was in tort
the Court of Appeal in a case like The Parana followed the later decision.
19
The approach in tort will, however, normally be different simply because
the relationship of the parties is different. The claim against the tortfeasor
who has inflicted tortious damage is not the same as the claim against an
opposite party for breach of contract for the latter claim depends on the
contemplation of the parties to the contract and questions of remoteness as
such do not arise. Consequently liability in tort may often be of a wider
kind. The observations of Willes, J. in Home v. Midland Railway Co.
L.R. 7 C.P. 583 at page 590 state the distinction in clear language in the
passage cited by my noble and learned friend Lord Reid and I agree that
this passage is to be preferred to the opinion sometimes expressed that the
measure of damages is the same in tort as it is in contract.
It seems that Mellish, L.J. in The Parana (supra) took a different view
of the rule in Hadley v. Baxendale when he said:
” In order that damages may be recovered, we must come to two
” conclusions—first, that it was reasonably certain that the goods would
” not be sold until they did arrive ; and, secondly, that it was reasonably
” certain that they would be sold immediately after they arrived, and
” that that was known to the carrier at the time when the bills of lading
” were signed.”
With respect to the Lord Justice this is putting the test too high. The con-
clusion reached on the facts of the case in The Parana need not however
be criticised because the voyage took about twice as long as might have been
expected and no reasonably accurate prediction of the length of the voyage
could be expected. He did, however, make use of the general observations
which have no doubt been treated as laying down a practice to be followed.
In reaching the conclusion that the Registrar and merchants were right
in their report he stated:
” They said that it had never been the practice in the Court of
” Admiralty to give such damages, and though it constantly happened
” that by accidents such as collisions goods were delayed in their arrival,
” it never had been the custom to include in the damages the loss of
” market; and we are of opinion that the conclusion which the Registrar
” and merchants came to was right.”
This decision has been treated as authoritative by text writers in this
country and has never been over-ruled but the rule of practice which it
purports to lay down is not followed universally and is insecurely based.
In the United States of America it seems that the Courts have never
followed the principle of assessment of damages laid down in The Parana.
Salmon, L.J. has pointed out that in the Corpus Juris Secundum, Vol. 80,
para. 124, it is stated that “In the ordinary case of deviation or delay, the
measure of damages is the difference in the market value of the goods at
the time when actually delivered and when they should have been delivered.”
In the case of the United States v. Middleton et al. (1924) 3 F (2d) 384 and
in other cases in the United States of America this position has been accepted.
It would, I think, be unfortunate if the law as to the measure of damages
based on the decision in Hadley v Baxendale in the two countries should
be held to have developed on different lines and I am glad to find that in my
opinion it has not in truth done so.
I have not dealt in detail with the facts of the instant case. These have
been sufficiently set out in the opinion of my noble and learned friend Lord
Reid. I need only say that I agree with the majority of the Court of Appeal
that, on the correct application of the decision in Hadley v. Baxendale to the
facts stated in the Special Case, although no special circumstances bring the
second rule in Hadley v. Baxendale into operation, the Appellant is liable
in damages for breach of contract in the larger sum awarded, viz.
£4,188 10s. 8d., a sum which includes damages for loss of market which in
this case arise ” according to the ordinary course of things “.
I do not find it necessary to say that the decision in The Parana was wrong
on the facts. Somehow or other from the language used in the judgment it
20
appears to have been elevated to a pronouncement on legal principle which is
not sustainable.
Lastly there is, in my opinion, no need to enter into the difficult question
Whether there may be differences between cases of non-delivery by carriers
and cases of delay by them. Certain decisions upon this topic have been
criticised and I express no opinion about them.
I would dismiss the appeal.
Lord Pearce
MY LORDS,
In Hadley v. Baxendale the Court attempted to clarify and define the
boundaries of damages in contract. In the Wagon Mound [1961] AC 388
the Privy Council attempted a similar task with regard to damages in tort.
In the present case (as in the Wagon Mound No. 2 (reported as Overseas
Tankship (U.K.), Ltd. v. Miller Steamship Co. Pty. Ltd. [1966] 2 All. E.R.
709)) it was suggested in argument that there was or should be one principle of
damages for both contract and tort and that guidance for one could be
obtained from the other. I do not find such a comparison helpful. In the
case of contract two parties, usually with some knowledge of one another,
deliberately undertake mutual duties. They have the opportunity to define
clearly in respect of what they shall and shall not be liable. The law has
to say what shall be the boundaries of their liability where this is not ex-
pressed, defining that boundary in relation to what has been expressed and
implied In tort two persons, usually unknown to one another, find that the
acts or utterances of one have collided with the rights of the other, and the
Court has to define what is the liability for the ensuing damage, whether
it shall be shared, and how far it extends. If one tries to find a concept of
damages which will fit both these different problems there is a danger of
distorting the rules to accommodate one or the other and of producing a rule
that is satisfactory for neither. The problems certainly have one thing in
common. In both the use of words with differing shades of meaning in the
various cases makes it hard to discern with exactitude where the boundaries
lie. See Wagon Mound No. 2 [1966] 2 All ER 709 at 713.
The underlying rule of the common law is that ” where a party sustains a
” loss by means of a breach of contract he is, so far as money can do it, to
” be placed in the same situation with regard to damages as if the contract
” had been performed ” (Baron Parke in Robinson v. Harmon 1 Ex. 850).
But since so wide a principle might be too harsh on a contract-breaker in
making him liable for a chain of unforeseen and fortuitous circumstances,
the law limited the liability in ways which crystallised in the rule in Hadley
v. Baxendale. This was designed as a direction to juries but it has become
an integral part of the law.
Since an Olympian cloud shrouded any doubts, difficulties and border-line
troubles that might arise in the jury room and the jury could use a common
sense liberality in applying the rule to the facts, the rule worked admirably
as a general guidance for deciding facts. But when the lucubrations of
judges who have to give reasons superseded the reticence of juries, there
were certain matters which needed clarification. That service was well per-
formed by the judgment of the Court of Appeal in the case of the Victoria
Laundry (Windsor) Ltd. [1949] 2 K.B. 528. I do not think that there was
anything startling or novel about it. In my opinion it represented (in felici-
tous language) the approximate view of Hadley v. Baxendale taken by many
judges in trying ordinary cases of breach of contract.
It is argued that it was an erroneous departure from Hadley v. Baxendale
in that it allowed damages where the loss was “a serious possibility” or
” a real danger ” instead of maintaining that the loss must be ” probable “, in
the sense that it was more likely to result than not. But, over twenty years
21
before, in Hall v. Pim (1927) 33 Com. Cas. 324. Lord Dunedin had said
(at 330) that it was enough if there was an even chance of the loss happening.
Lord Shaw (at 334) said that the two parts of the rule need not be anti-
thetically treated but might run into each other and be one; and (at 335)
he read probable as meaning a “not unlikely” result. Lord Phillimore
(at 336) said:
” [They] are called damages in contemplation of the parties, not
” because the parties contemplate a breach of contract, but because
” they recognise that a breach is possible, and they reckon that these
” damages may flow from that breach. I designedly use the word
” ‘ may’. There may be cases where the word to be used might be
” ‘ will’, but there are also cases, and more common cases, where the
” word to use is ‘ may’.”
Lord Blanesburgh expressed agreement with the others, and presumably
did not dissent from the views set out above. Lord Haldane (at 327) dealt
with the matter as one of construction: ” Whether such a resale was likely
” or not does not matter if, as I think, the buyers stipulated for power to
” make it being provided.”
I believe that even at that date those observations would not be regarded
as novel. And the fact that the case was not included in the Law Reports
may be some slight confirmation of this belief. Inevitably there is some
evolution of thought in such matters, and such as there was tended in the
direction of taking a wider view of probability. In 1948 in The Monarch
Steamship Co., Ltd. [1949] AC 196, a case of damages for delay in
carriage by sea. Lord Du Parcq (at 233) used the words ” at least a serious
” possibility” and ” a real danger which must be taken into account.”
Lord Uthwatt (at 232) spoke of ” the chance of war, not as a possibility
” of academic interest . . . but as furnishing matter which commercially
” ought to be taken into account.” And Lord Morton of Henry ton spoke
of ” a grave risk ” (235).
Accordingly in my opinion the expressions used in the Victoria Laundry
case were right. I do not however accept the colloquialism ” on the cards ”
as being a useful test because I am not sure just what nuance it has either
in my own personal vocabulary or in that of others. I suspect that it owes
its attraction, like many other colloquialisms, to the fact that one may
utter it without having the trouble of really thinking out with precision what
one means oneself or what others will understand by it, a spurious attraction
which in general makes colloquialism unsuitable for definition, though it is
often useful at shorthand for a collection of definable ideas. It was in this
latter convenient sense that the judgment uses the ambiguous words ” liable
” to result”. They were not intended as a further or different test from
” serious possibility ” or ” real danger “.
The whole rule in Hadley v. Baxendale limits damages to that which may
be regarded as being within the contemplation of the parties. The first
part deals with those things that ” may fairly and reasonably be considered
” as arising naturally, i.e. according to the usual course of things “. Those
are presumed to be within the contemplation of the parties. As Lord
Wright said in the case of the Monarch Steamship [1949] AC 196 at 224:
” As reasonable business men each must be taken to understand the
” ordinary practices and exigencies of the other’s trade or business.
” That need not generally be the subject of special discussion or
” communication “.
After referring to the Banco de Portugal case [1932] AC 452 he continued:
” Both parties were tacitly taken to be acquainted sufficiently with
” the general business position. The same is true in many cases of
” complicated consequences flowing from an unanticipated breach of
” contract, but the damages are not treated either as special or remote
” if they flow from the normal business position of the parties which
” the court assumes must be reasonably known to them. It would not
22
” be helpful to cite the familiar authorities which are numerous but
” depend primarily upon the facts of each case.”
Even the first part of the rule however contains the necessity for the know-
ledge of certain basic facts e.g. in Hadley v. Baxendale the fact that it was
a mill shaft to be carried. On this limited basis of knowledge the horizon
of contemplation is confined to things ” arising naturally, i.e. according to
” the usual course of things “.
Additional or ” special” knowledge, however, may extend the horizon to
include losses that are outside the natural course of events. And of course
the extension of the horizon need not always increase the damages ; it
might introduce a knowledge of particular circumstances e.g. a subcontract,
which show that the plaintiff would in fact suffer less damage than a more
limited view of the circumstances might lead one to expect. According to
whether one categorises a fact as basic knowledge or special knowledge
the case may come under the first part of the rule or the second. For that
reason there is sometimes difference of opinion as to which is the part
which governs a particular case and it may be that both parts govern it.
I do not think that Baron Alderson was directing his mind to whether
something resulting in the natural course of events was an odds-on chance
or not. A thing may be a natural (or even an obvious) result even though
the odds are against it. Suppose a contractor was employed to repair the
ceiling of one of the Law Courts and did it so negligently that it collapsed
on the heads of those in Court. I should be inclined to think that any
tribunal (including the learned Baron himself) would have found as a fact
that the damage arose ” naturally i.e. according to the usual course of
” things”. Yet if one takes into account the nights, week ends, and
vacations, when the ceiling might have collapsed, the odds against it
collapsing on top of anybody’s head are nearly ten to one. I do not believe
that this aspect of the matter was fully considered and worked out in the
judgment. He was thinking of causation and type of consequence rather
than of odds. The language of the judgment in the Victoria Laundry case
was a justifiable and valuable clarification of the principles which Hadley
v. Baxendale was intending to express. Even if it went further than that,
it was in my opinion right.
Nor do I consider that the Victoria Laundry case is inconsistent with the
actual decision on the facts in Hadley v. Baxendale. The carriers were asked
(without special directions, as the Court found) to transport a broken shaft
away from a mill. ” In the great multitude of cases ” (to quote the learned
Baron’s own phrase)—one would not expect the whole working of a mill
to be stopped by a delay in transportation. The mere absence of urgent
instructions spoke strongly against such a contingency. The fact that the
shaft was to be used immediately by engineers for measurements (which one
would have rather expected to go on paper by post) for making a new shaft
would not, I think, have been in the contemplation of the carriers, on the
meagre information available.
The facts of the present case lead to the view that the loss of market arose
naturaly, i.e. according to the usual course of things, from the shipowner’s
deviation. The sugar was being exported to Basrah where, as the
Respondents knew, there was a sugar market. It was sold on arrival and
fetched a lower price than it would have done had it arrived on time. The
fall in market price was not due to any unusual or unpredictable factor.
Had this been a case of non-delivery on sale of goods whether by sea or
land it is uncontested that the defendants would be liable for the loss of
market. Had it been a case of delay in sale of goods the prima facie rule
is that the damage is the difference between ” the value of the article con-
” tracted for at the time when it ought to have been and the time when it
” actually was delivered ” (per Blackburn J. Elbinger Actien-Gesellschafft v.
Armstrong L.R. 9 Q.B. 473 at 477. Nor can it really be contended that it
would have been otherwise if this had been a case of delayed delivery in
carriage by land. For this has been long established by such cases as
23
Collard v. South Eastern Railway Company 158 E.R. 400; Wilson v.
Lancashire and Yorkshire Railway Company 142 E.R. 248; and Horne v.
Midland Railway Company 7 C.P. 583 ; 8 C.P. 131.
It is however argued that different considerations arise in delay in carriage
at sea. The decision in The Parana 2 P.D. 118, it is said, established a
special principle or practice with regard to delay in carriage by sea which
should apply to this case and should confine the damages to loss of interest
on the value of the goods. The Court of Appeal in The Parana appeared
to decide largely on the ground that it was not ” reasonably certain ” that
the goods would not be sold until they arrived and that they would be sold
as soon as they did arrive. The estimates of the duration of the voyage
appear to have varied between 65 days and 90 days; and in fact it took
127 days. And no doubt the chief factor which influenced the Court was
that ” the uncertainties of the voyage were so great that the parties could
” not be said to have contracted on the footing that the goods would arrive
” at any particular moment”. Sir Richard Henn Collins M.R. said this
when he dealt with The Parana in Dunn v. Bucknall Bros. [19021 2 K.B.
614 at 623. He pointed out that ” It is certainly not a rule of law but an
” inference of fact that from the circumstances of the case no reasonable
” assumption as to the state of the market at the time of arrival could have
” been a factor in the contract between the parties “. In the latter case the
Court did award damages for loss of market. So too in The Ardennes [1951]
1 K.B. 55).
In the United States the Corpus Juris Secundum states that ” In the
” ordinary case of deviation or delay, the measure of damages is the
” difference in the market value of the goods at the time when actually
” delivered and when they should have been delivered, with interest”. In
1924 in Middleton’s case (3 Fed. Rep. 2nd Series 384 at 393) His Honour
Judge Rose of the Federal Court of Appeals said:
” The Parana was decided 47 years ago. It is by no means certain that,
” even in England, it would now be unhesitatingly followed. . . .
” Nearly half a century has elapsed since the decision of The Parana and
” more than two decades since that of Dunn v. Bucknall Bros. In the
” meanwhile steam has more and more taken the place of the shift-
” ing winds as the motive power upon the sea, with the result that the
” duration of voyages may now be calculated with at least some approach
” to certainty, even when they are to the ends of the earth. In these
” days merchants make their calculations accordingly, and it is not
” unreasonable to insist that shipowners shall do the like. There would
” seem to be little injustice in so doing, when it is remembered that they
” are not answerable at all when they are able to show that the delay
” was caused by something which due diligence on their part was
” powerless to prevent.”
In The Parana (and in the present case) reliance was placed on the fact
that in cases of carriage by sea the goods are likely to have been sold in
transit while still afloat and that therefore the shippers would not suffer by
their late arrival. But, if they were so sold, under the bill of lading the buyer
would stand in the shoes of the shipper, would suffer the loss, and would
sue in respect of it. This fact makes the contemplation of the loss neither
more nor less likely.
In my opinion the line of approach in Dunn v. Bucknall Bros, and in the
United States cases is correct. In most cases the loss of market will be found
to be within the contemplation of the parties in carriage of goods by sea.
It is however ultimately a question of fact. And it may be that in some
unusual cases it will be found that the situation between the parties showed
that the shipper was indifferent to the time of arrival and that the parties did
not contract on the basis that in case of deviation or delay the shipowner
should be liable for loss of market. But the absence of an express clause
(which could easily be inserted) to that effect will obviously make it hard to
establish. I have not dealt with the various particular facts in this case by
24
which Mr. Kerr’s able argument seeks to show that these particular parties
did not contemplate damage by loss of market. For I agree with the remarks
of the majority of the Court of Appeal on this subject.
Accordingly if The Parana purported to lay down any general proposition
or rule of law, it was wrongly decided. Even if it was merely purporting
to draw an inference of facts from the particular case, I have some doubt of
its correctness even at that date, and it has no applicability to-day. And in
my opinion The Notting Hill 9 P.D. 105 which applied The Parana to a case
of tort, was wrongly decided.
I would dismiss the appeal.
Lord Upjohn
MY LORDS,
This appeal is concerned solely with the proper measure of damages for
an admitted breach of contract by a shipowner resulting in the late delivery
of a cargo which he contracted to deliver to the port of discharge. The
practical question is whether the charterer can claim damages for loss of
market as the cargo of sugar was to be delivered to a port where there is a
market in that commodity.
The general principle upon which damages are assessed for breach of
contract is succinctly stated by Baron Parke in Robinson v. Harmon 1 Ex. 850
at page 855—” Where a party sustains a loss by reason of a breach of
” contract he is, so far as money can do it, to be placed in the same situation
” with respect to damages as if the contract had been performed “, a statement
approved in your Lordships’ House in Watts, Watts & Co. Ltd. v. Mitsui
& Co. Ltd. [1917] A.C. 227 at 241. The same rule has been laid down in
your Lordships’ House for the assessment of damages generally including
torts (see Livingstone v. Rawyards Coal Co. 5 A.C. 25 at page 39.
Such general principles were, however, applied rather strictly for until
Hadley v. Baxendale 9 Ex. 341, decided in 1854, the rule was that the damage
resulting must be the proximate damage: thus in Smeed v. Foord (1 El. &
El. 602) during argument when Hadley v. Baxendale was under discussion
Campbell, C.J. interjected at page 608—” The old rule was that, in estimating
” damages, only the proximate injury sustained could be looked to “. With
the increasing complications of life and the upsurge of industrial activities
these simple rules failed to give sufficient guidance to juries or indeed judges
for the assessment of damages for breach of contract in more complicated
cases. But when Messrs. Hadley, owners of a flour mill in Gloucester,
having sent a broken mill shaft by the well-known carriers Pickfords to their
suppliers in Greenwich to provide a pattern for a new shaft and there being
a delay in delivery by Pickfords amounting to a breach of contract, claimed
damages on the footing that the whole activities of their mill were held up
for want of the shaft, it was clear that the rule, though requiring some
expansion, must nevertheless receive some limitation. This led to the famous
statement of Alderson B. in that case 9 Ex. 341 at page 354.
” Now we think the proper rule in such a case as the present is this: —
” Where two parties have made a contract which one of them has
” broken, the damages which the other party ought to receive in respect
” of such breach of contract should be such as may fairly and reason-
” ably be considered either arising naturally, i.e., according to the usual
” course of things, from such breach of contract itself, or such as may
” reasonably be supposed to have been in the contemplation of both
” parties, at the time they made the contract, as the probable result of
” the breach of it. . . . “
Though stated by the learned Baron in one sentence it contains and has
always been interpreted as containing two branches and for my part I .care
not whether it is regarded as stating two rules or two branches of one rule,
though I prefer the latter. Thus:
25
-
-
-
Damages should be such as may naturally and usually arise from
the breach, or -
Damages should be such as in the special circumstances of the case
known to both parties may be reasonably supposed to have been
in the contemplation of the parties, as the result of a breach, assum-
ing the parties to have applied their minds to the contingency of
there being such a breach.
-
-
See Hammond and Co. v. Bussey 20 Q.B.D. 79 approved in this House in
R. & Hall Ltd. v. W. H. Pim (Junior) & Co., Ltd. 33 Com. Cas. 324. How-
ever there is no dichotomy between these branches for as Lord Shaw pointed
out in the last-mentioned case at page 334 ” they may run into each other
” and indeed be one “.
In British Columbia & Vancouver Island Spar, Lumber & Saw-Mill Co.
Ltd. v. Nettleship L.R. 3 C.P. 499 it was decided on the second branch of
the rule that there must not only be common knowledge of some special
circumstances but liability for damages resulting therefrom must be made
a term of the contract. This was followed in Home v. Midland Railway Co.
L.R. 8 C.P. 131. I do not see why that should be so. If parties enter
into the contract with knowledge of some special circumstances, and it is
reasonable to infer a particular loss as a result of those circumstances that
is something which both must contemplate as a result of a breach. It is
quite unnecessary that it should be a term of the contract. I agree with the
learned editor of the Third Edition of Halsbury Vol. 11 page 243 note (m)
that those authorities ought not to be followed. In any event, as Diplock
L.J. has pointed out, this point had little application in practice.
So the claim for damages must be the natural consequence of the breach
or in the contemplation of both parties. But in tort a different test has
been adopted in expanding the basic law of damages and I cannot accept
the argument addressed to your Lordships that they remain the same. The
test in tort, as now developed in the authorities, is that the tortfeasor is
liable for any damage which he can reasonably foresee may happen as a
result of the breach however unlikely it may be, unless it can be brushed
aside as far fetched. See the Wagon Mound cases [1961] AC 388 ; [1966]
3 W.L.R. 498.
This difference is very reasonable. Once an examination of the facts
establishes a breach of duty on the part of the tortfeasor, the acts and
omissions of the innocent party are irrelevant until the question of con-
tributory negligence comes to be considered. A tortfeasor may and frequently
is a complete stranger to the innocent party but he is, however fleetingly
in many cases, his neighbour for the purposes of the law and bound to act
with due regard to his neighbour’s rights whoever he may be. If he fails
in such duty the law has rightly laid down a more stringent test for the
assessment of damages. But in contract the parties have only to consider
the consequences of a breach to the other; it is fair that the assessment
of damages should depend on their assumed common knowledge and con-
templation and not on a foreseeable but most unlikely consequence. The
parties may moreover agree to limit or exclude liability for damage, or
agree on a liquidated sum, or one party can disclose to the other special
circumstances which will render a breach especially serious to him. So the
rules as to the assessment of damages have diverged in the two cases, and
nowadays the concept of ” foreseeability” and ” contemplation of the
” parties ” are different concepts in the law. It is true that as a matter of
language there will in many cases be no great difference between foreseeing
the possibility of an event happening and contemplating the possibility of that
event happening and in some of the cases, from Lord Blackburn in Cory v.
Thames Ironworks L.R. 3 Q.B. 181 at 188 onwards the word foresee or
foreseeable is used in connection with contract but it is clear that it has really
been used in the sense of reasonable contemplation and in my view it is
better to use contemplate or contemplation in the case of contract, leaving
foresee or foreseeability to the realm of torts.
26
The rule in Hadley v. Baxendale was approved in express terms in Bank
of Portugal v. Waterlow [1932] AC 452 and in The Monarch Steamship
Co., Ltd. v. Karlshamns Oljefabriken (A/B) [1949] A.C. 196, and has been
followed in a multitude of cases ever since it was decided. I think that apart
from some very early criticisms it would be true to say that it stood without
question until the case of Victoria Laundry (Windsor) Ltd. v. Newman
Industries Ltd. [1949] 2 K.B. 528 when it received a colourful interpretation
from Asquith L.J. delivering the judgment of the Court.
My Lords, in my opinion this appeal renders it necessary to determine the
following questions:
(1) Has the Victoria Laundry case purported to alter the law and estab-
lish a somewhat different rule from that laid down in Hadley v.
Baxendale for the assessment of damages in contract;
(2) What, as a practical matter, is the test to be applied in ascertaining
whether any particular consequences of a breach of contract should
lead to recoverable damages as arising either naturally or such as
may have been within the contemplation of the parties in the special
circumstances of the case ;
(3) Applying that test, what on the facts of this case is the proper
measure of damages ; unless
(4) Is there some special rule of practice in relation to carriage of
goods by sea established by The Parana [1877] 2 P.D. 118 which
precludes the recovery of damages beyond interest on the value of
the goods over the period of the delay, unless the plaintiff can bring
the case on its special circumstances within the second branch of
the rule.
(1) Upon the first point it is, I think, clear that on a fair reading of the
judgments of the majority of the Court of Appeal they considered that the
Victoria Laundry case did alter the law. That case was one plainly within
the second branch of the rule, but nevertheless the observations of Asquith
L.J. were in general terms applicable to both branches. I do not myself
think that the learned Lord Justice intended to alter the law. He was para-
phrasing it and putting it into modern language, and I shall refer to this
under the next heading. If he was doing more, I would disagree with him.
But for my part I prefer to state the broad rule as follows:
What was in the assumed contemplation of both parties acting as
reasonable men in the light of the general or special facts (as the case
may be) known to both parties in regard to damages as the result
of a breach of contract;
I omit for the moment any adjectival qualification of the result which I deal
with in (2) below Lord Wright pointed out in The Monarch (supra) at 224
that each must be taken to understand the ordinary practices and exigencies
of the other’s trade but it must be remembered when dealing with the case
of a carrier of goods by land, sea or air, he is not carrying on the same trade
as the consignor of the goods and his knowledge of the practices and exigencies
of the other’s trade may be limited and less than between buyer and seller of
goods who probably know far more about one another’s business.
(2) Upon the second point, what as a practical matter is to be taken as
within the contemplation of both parties as the result of a breach? The
words ” probable result” held the field at first; they were used in the
enunciation of the rule itself and by Esher M.R. in Hammond v. Bussey
(supra) and adopted by Lord Dunedin in Hall v. Pim (supra) at 330 who,
however, was careful to add that ” probable ” in his view did not mean more
than an even chance. Lord Shaw in that case interpreted the word probable
in the sense of the not unlikely result (page 334). In The Monarch their
Lordships used a variety of different expressions. I will very briefly enumerate
them,—likelihood ; possibility must have been in the minds of both parties;
a matter commercially to be taken into account; a serious possibility or a
real danger ; a grave risk.
27
Asquith LJ. in Victoria Laundry (supra) used the words ” likely to result”
and he treated that as synonymous with a serious possibility or a real danger.
He went on to equate that with the expression “on the cards” but like
all your Lordships I deprecate the use of that phrase which is far too im-
precise and to my mind is capable of denoting a most improbable and unlikely
event, such as winning a prize or a premium bond on any given drawing.
But in my opinion Asquith L.J. was not attempting to do more than explain
the rule in the light of the observations made in this House in The Monarch.
It is curious that Hall v. Pim seems to have escaped citation in all the later
cases until this appeal to your Lordships
It is clear that on the one hand the test of foreseeability as laid down in
the case of tort is not the test for breach of contract; nor on the other hand
must the loser establish that the loss was a near certainty or an odds-on
probability. I am content to adopt as the test a “real danger” or a
” serious possibility “. There may be a shade of difference between these
two phrases but the assessment of damages is not an exact science and what
to one judge or jury will appear a real danger may appear to another judge
or jury to be a serious possibility. I do not think that the application of
that test would have led to a different result in Hadley v. Baxendale. I
cannot see why Pickfords in the absence of express mention should have con-
templated as a real danger or serious possibility that work at the factory
would be brought to a halt while the shaft was away.
(3) Applying this test to the facts of this case the first and most important
matter for consideration is the contract contained in the Charter Party which
was dated 15th October, 1960. It provided that the Heron II should pro-
ceed to Constanza and there load 3,000 tons of sugar and then proceed with
all convenient speed to Basrah. At the date of the contract the ship was
dry-docked in Piraeus and was expected to be ready to load about 25/27th
October, so it was provided that lay days were not to run before then. It
was further provided that if the ship was not ready to load by 10th November,
1960, the charterers were to have the option to cancel the Charter Party.
The charterers were also given the option of discharging the cargo at Jeddah
to be declared 5 days before the commencement of loading. The distance
from Constanza to Basrah is 4,370 miles and a reasonably accurate predic-
tion of the length of the voyage was 20 days. The Heron II arrived at
Constanza on 27th October duly loaded and sailed on 1st November, 1960.
Due to a number of breaches of contract which I need not specify the vessel
took 29 days to complete the voyage instead of the predicted 20. The ship-
owner knew of the existence of a sugar market at Basrah but had no detailed
knowledge thereof. Those in essence are the relevant facts upon which the
question of damages has to be determined. It is common ground that the
question falls within the first branch of the rule in Hadley v. Baxendale.
Both McNair J. in the Court of first instance and Sellers L.J. in his dis-
senting judgment in the Court of Appeal were impressed by the fact that the
ship might lawfully have presented itself for loading at any time up to
10th November and might have been directed to go to Jeddah and this cir-
cumstance influenced each of them in reaching the conclusion that loss of
market due to delay could not have been within the contemplation of the
parties. I cannot agree with this; Diplock and Salmon L.JJ., have, in my
opinion, answered this point. The cancellation clause was put in to protect
the charterer from undue delay if the repairs to the ship in dry-dock should
take longer than anticipated ; its existence does nothing in my opinion to alter
the common contemplation of the parties as to the consequences of a failure
of the ship to carry out the primary obligation to proceed on its journey with
all convenient speed ; if anything it supports the view that time was an
important element in the voyage. Nor can I see the relevance of the fact
in this respect that another port of discharge might have been designated.
It was not and the Heron II was under contract to carry with all convenient
speed one cargo to one port of discharge where there was a market for that
cargo.
28
This case is quite different from those cases where cargo ships used
in the old days literally to tramp up and down, for example, the Mediter-
ranean, with liberty to call at any port in any order (though that phrase,
as the authorities show, must receive a limited and not a literal con-
struction) collecting and discharging cargo as they steamed from port to
port; so that delay in carrying a cargo to a particular port within a particular
time or even with all convenient speed cannot have been within the con-
templation of the parties as giving rise to damage for loss of market—
see, for example, Connolly Shaw, Ltd. v. A/S Det Nordenfjeldske D/S
49 LI. L. Rep. 183 at page 191 per Branson J. The Ardennes 84 LI. L. Rep.
340 might have been such a case if the facts had not brought it clearly within
the second branch of the rule.
It has long been established that in carrying marketable goods by rail
to a place where there is a market it must be assumed to be in the contem-
plation of the parties as a grave danger that the goods may be sold on arrival
so that if there is a delay one of the consequences may be loss of market.
See Collard v. South Eastern Railway Company 7 H. & N. 79 and Home
v. Midland Railway (supra). The plaintiff failed in the last case because
there was no market loss and he failed to communicate the circumstances
which led to his special loss. Is there any reason why this rule should not
in principle apply to carriage of goods by sea?
As long ago as 1902 in the case of Dunn v. Bucknall Brothers [1902]
2 K.B. 614 Collins M.R. pointed out that sea voyages of three to four
weeks duration are accomplished with almost absolute certainty and the
state of the market may well be a vital fact present to the minds of both
parties at the time of making the contract.
In Jensen v. Hollis Bros. & Co., Ltd. 54 L1. L. Rep. 133 Branson J. at
page 137 did not over-exaggerate when he said that ships with modern
facilities run with somewhat of the regularity of railway trains. So I see no
reason why in principle the normal rule as to carriage of goods by land
should not apply to the type of voyage undertaken by the Heron II. I do not
refer to the authorities to which your Lordships were referred where there
is a complete loss of, or some physical damage to, goods such as Rodocanachi
v. Milburn 18 Q.B.D. 67, for though the same general principles apply,
both Lord Dunedin and Lord Atkinson pointed out in Williams v. Agius
[1914] A.C. 510, that there are substantial differences in practice between
late delivery and non-delivery. Where marketable goods are lost it is
almost axiomatic that the market price measures the damage ; the same
cannot be said of delay ; it all depends on circumstances. Different con-
siderations apply to cases between buyer and seller, as I have already
pointed out. Nor do I think it necessary to discuss Wertheim v. Chicoutimi
Pulp Co. [1911] AC 301 and the criticisms of Scrutton L.J. of that case
in Slater v. Hoyle & Smith [1920] 2 K.B. 11 ; that controversy was really
concerned with the measure of damages on subsales.
But the Heron II took very nearly fifty per cent more than the reasonably
predicted time and for no other reason than her owner’s breaches of
contract.
It is perfectly true that at the time of the contract nothing was said as to
the purpose for which the charterer wanted the sugar delivered at Basrah ;
he might have wanted to do so to stock up his supply of sugar or to carry
out a contract already entered into which had nothing to do with the market
at Basrah; or he might sell it during the voyage, but all that is pure
speculation. It seems to me that on the facts of this case the parties must
be assumed to have contemplated that there would be a punctual delivery
to the port of discharge and that port having a market in sugar there was
a real danger that as a result of a delay in breach of contract the charterer
would miss the market and would suffer loss accordingly. It being estab-
lished that the goods were in fact destined for the market the shipowner
is liable for that loss.
(4) I turn, then, to the last question. Does The Parana (supra) lead to the
conclusion that in the case of carriage of goods by sea there is a different
29
rule of practice; it is not suggested that there is any different rule of law.
McNair J. and Sellers L.J. thought so and that damages were limited to
loss of interest on the value of the goods detained.
No doubt in the days of sail pure and simple, when ships might be delayed
by head winds for days, loss of market would not be within the contemplation
of the parties. In 1877, when The Parana was decided, the steam engine
was coming into its own but it was still the golden age of sail and over
half the ships built in this country were sailing ships at this time; these
matters may well have influenced Mellish L.J. when he pointed out the
difference between delay in delivery by carriers on land and cases of
carriage of goods on long voyages by sea. Perhaps he was right as matters
then stood, but the rapid improvement in the steam engine led to a different
statement of principle in Dunn v. Bucknall Bros, (supra) a statement in accordance with general principle and which must govern the assessment of damages today. The Parana, which has only once been followed in
Notting Hill 9 P.D. 105 and frequently criticised, must be regarded as either
obsolete, being overtaken by events or as overruled. It may be noted that
The Parana was not treated by Mellish LJ. as a tramp steamer in the sense
in which I have used that phrase earlier in this judgment.
In Dunn v. Bucknall (supra) an explanation of the decision in The
Parana was suggested, that the estimates of the proper time for completion
of the voyage of the Parana varied very greatly so that the time of arrival
was not predictable. This explanation was not given by Mellish L.J.
himself and I doubt if it is valid.
Even today, when very long journeys half-way round the world are under-
taken, the estimate of the time which a ship ought to take may vary within
wide limits; see, for example, two cases in the U.S.A., the United States v.
Middleton 3 Fed. Reporter 2nd Series 384 (an Atlantic port to Japan
60 to 90 days) and the Iossifoglu 32 Fed. Reporter 2nd Series 928 (Phillipines
to a U.S. Atlantic port 46 to 66 days). Nevertheless in both those cases
it was held that in the case of marketable commodities being carried to a
market, if the ship greatly exceeds the larger estimate through breach of
contract and the cargo owner thereby misses his market he is entitled to
damages for loss of market. I agree with those decisions, so far as the
Judges who decided those cases felt no difficulty by reason of the fact that
the time of arrival could only be estimated within broad limits.
For these reasons I would dismiss this appeal.
Source: https://www.bailii.org/



