SHELL BP PETROLEUM DEVELOPMENT COMPANY LTD. V. JAMMAL ENGINEERING
(1974) LCN/1794(SC)
In the Supreme Court of Nigeria
Thursday, April 11, 1974
Case Number: SC. 100/1970
RATIO
DAMAGES: DETERMINING THE MEASURE OF DAMAGES
The measure of damages appropriately is the loss flowing from the contract and unless the element of speculation was in the contemplation of the parties at the time of the contract, whatever else could have accrued to a party as a result of that speculation on the contract is not relevant. That was in effect the decision of the House of Lords in the case of Bain v. Fothergill (supra). In Wright v. Dean (supra), Wynn Parry, J., as he then was, explained and applied the principle expounded in Hadley v. Baxendale (supra). We are in agreement with his explanation and application of that principle. Hollington Brox. v. Rhodes (supra) is a classic example of an assessment of damages based on actual expenses incurred by the plaintiffs as a necessary result of the breach by the defendants of their contract in that case. The principle of assessment established by the authorities is clear generally. It is that a party in breach of his contract is liable in damages and the aggrieved party is entitled to such an owing necessarily from the breach in that either the injury suffered by the aggrieved was in the contemplation of both parties at the time of the institution of the contract or is an inevitable consequence of the breach. With respect to the case in hand, as we have stated before, such damages must be assessed with reference to any loss actually suffered by the plaintiffs as a result of the defendants’ breach to let the houses to them: the loss calculated not on the figures of what possibly they could have expended or suffered but on the figures of what they actually expended or suffered.
The learned trial judge had found that there was no evidence from the plaintiffs on this aspect of the case (he described it undoubtedly erroneously as “special damages”) and indeed before us learned counsel for the plaintiffs conceded that there was no such evidence. In that case plainly there should have been no award, not because the plaintiffs are not entitled to it but because they failed to supply the necessary materials on which an assessment of their loss or damages can be based. PER COKER, J.S.C.
DAMAGES: THE RULE ON THE ASSESSMENT OF DAMAGES
The law with regard to the assessment of damages was laid down as far back as 1854 in the case of Hadley v. Baxendale (1854) 9 Ex (Ch. 341, where at p. 354 of the Report, Alderson, B. expressed the law as follows:
“Now we think the proper rule in such a case as the present is this: Where two parties have made a contract which one of them has broken, the damages which the other party ought to receive in respect of such a breach of contract should be such as may fairly and reasonably be considered either arising naturally, according to the usual course of things, from such breach of contract itself, or such as may reasonably be supposed to have been in the contemplation of both parties, at the time they made the contract, as the probable result of the breach of it.”
The formula does not leave any room for any further classification of damages into general or special for whatever species of damage it be, to be sustainable such damage must flow naturally from the breach of the contract in the sense that it was contingent or dependent upon a matter or factor expressly or impliedly within the contemplation of the parties to the contract at the time of its institution. The categorisation into general and special damages is exceptionally confusing and in some cases had occasioned substantial miscarriage of justice. See Chanrai & co. (Nigeria) Ltd. v. Khawam (1965) 1 All N.L.R. 182; also Maiden Electronic Works Ltd. v. The Attorney-General of the Federation (1974) 1 S.C. 53 (especially at p. 97). PER COKER, J.S.C.
DISCRETION OF COURT: GRANTING AMENDMENTS OF PLEADINGS
The rules for granting amendments of pleadings or proceedings are very flexible and a great deal depends on the discretion of the judge or tribunal. Where there has been no breach of any relevant rule of law in that respect a party opposing the grant of leave to amend such pleadings or proceedings has a rather uneasy task and unless he can establish prejudice, unnecessary expense, irreparable inconvenience or lack of good faith, the hands of the court are free. In the present case, it was not shown and has not been shown to us that the learned trial judge did not properly exercise his discretion to grant leave to amend and we cannot accede to the ground of appeal which complains about this. PER COKER, J.S.C.
DUTY OF COURT: CONSIDERATION OF ALL CORRESPONDENCE
It was further argued that the learned trial judge should have confined his decision only to the documents produced by the plaintiffs to prove their case and that he should not have employed in deciding to give the plaintiffs judgment on the point those documents which the defendants had produced in evidence for the purpose of disproving the plaintiffs’ case. For this argument learned counsel for the defendants had placed reliance on the Footnotes No.5 to Order 18/12 of the Rules of the Supreme Court in England (Annual Practice 1970 at p. 362) which, under the caption “Agreement”, reads in part as follows:
“Where a contract is alleged to be implied from a series of letters or conversations or otherwise from a number of circumstances, the contract should be alleged as a fact, and the letters, conversations or circumstances set out generally, and further particulars requiring details will not generally be ordered.”
The Rule referred to does not purport to alter the existing law or rule of pleadings. All it says is that the pleadings of the parties must be cogent enough to give the other party notice of what is intended to be canvassed at the hearing. Neither the rule itself nor the Footnotes relied upon by learned counsel attempted to restrict the freedom of a judge in the eventual consideration of a case to put together and reassemble the facts before him. The final exercise of judgment must of necessity involve a consideration of all the correspondence that is properly put in evidence by both sides, all the correspondence tendered in order to establish the case and all that produced in order to disprove the existence of a contract. It is only after such detailed consideration that a tribunal can fairly come to a conclusion as to whether or not the parties actually arrived at an agreement. See Thomas Hussey v. Horne-Payne (1879) 4 App. Cas. 311. PER COKER, J.S.C.
JUSTICES:
WILLIAMS, JUSTICE, SUPREME COURT
COKER, JUSTICE, SUPREME COURT
IRIKEFE, JUSTICE, SUPREME COURT
APPELLANTS
SHELL BP PETROLEUM DEVELOPMENT COMPANY LTD
RESPONDENTS
JAMMAL ENGINEERING (NIGERIA) LIMITED
COKER, JSC. (Delivering the Judgment by the Court)
This appeal involves two cases which were consolidated for hearing by the High Court, Lagos State (Dosunmu, J.). The parties to both cases are the same save for the fact that the plaintiffs in one are the defendants in the other. In the first of the cases, i. e. Suit No. LD/160/69, the plaintiffs are Shell BP Petroleum Development Co. of Nigeria Ltd., and the defendants Jammal Engineering (Nigeria) Limited. The writ of summons in that case, as finally amended, is endorsed as follows:- “The plaintiff claims against the defendant: 1. A declaration that the agreement partly written partly oral made between the plaintiff and the defendant between June, 1968, and February, 1969, whereby the defendant agreed to lease to the plaintiff upon certain terms, properties situate at and being houses Nos. 11, 12, 13, 14 and 2 Jammal Estate, off Gerrard Road, Ikoyi is a valid and subsisting agreement and is binding upon the defendant. 2. An Order of specific performance of the said agreement. 3. £5,000 damages for defendant’s wrongful failure or neglect to complete the houses and deliver possession of the same at the time stipulated in the agreement. 4. An Injunction restraining the defendant its servants or agents or otherwise howsoever from leasing or parting with the possession of the said houses Nos. 11, 12, 13, 14 and 2 Jammal Estate, Gerrard Road, Ikoyi otherwise than by leasing the same to or by duly effectively vesting the same in plaintiff. Alternatively 5. Repayment of the said deposit of £2,500 together with interest thereon at the rate of 5 per centum per annum. 6. £12,750 being general damages for breach of the said agreement.”
The other action was commenced some five or six weeks later as Suit No. LD/243/69. The plaintiffs therein are Jammal Engineering (Nigeria) Ltd., and the defendants Shell BP Petroleum Development Co. of Nigeria Ltd. The writ is endorsed for the following claims:- “The plaintiff’s claim against the defendant is for a declaration that the “tenancy agreement” dated 14th March, 1969, and purporting to have been made by the plaintiff of the one part and the defendant of the other part is null and void and not binding on the plaintiff. In the alternative the plaintiff claims the said “agreement” is voidable and should be set aside.” Pursuant to the relevant order of court, pleadings were filed and delivered in both cases and at the trial, after consolidation, the learned trial Judge regarded the Shell BP Petroleum Development Co. of Nigeria Ltd., as plaintiffs and Jammal Engineering (Nigeria) Ltd., as defendants in the consolidated proceedings. We propose in this judgment to refer to the respective parties in the same manner. The pleadings of the plaintiffs aver that both the plaintiffs and the defendants are limited liability companies, that by agreement dated the 30th August, 1968, between the parties, the plaintiffs agreed to hire and the defendants agreed to let to them eight houses belonging to the defendants, five of which (i.e. Nos. 2, 11, 12, 13 and 14 in Jammal Estate, Ikoyi) are to be let for respective terms of three years starting from the dates of completion of each house at the yearly rent of £1,900 (or N3,800) per house, the first two years’ rents to be paid down and on terms to the effect that the lessees should pay all rates and execute all internal repairs and the lessors should pay the ground-rent and be responsible for all structural repairs. The plaintiffs’ statement of claim further stated in paragraphs 6 and 7 thereof as follows:- PAGE| 3 “6. The defendant company contracted that the said dwelling houses would be ready for occupation by the plaintiff on the following dates: House No. 11 ……. 12/2/69 House No. 12 ……. 22/2/69 House No. 13 ……. 15/3/69 House No. 14 ……. 15/3/69 House No. 2 ……. 22/3/69 7. In response to the demands of the defendants the plaintiff in January, 1969, paid to the defendant the sum of £2,500 as deposit representing advance payment of £500 rent in respect of each of the five houses.” The statement of claim further avers that although the defendants duly executed the leases of three out of the eight houses concerned in favour of the plaintiffs after the completion of those three houses, the defendants had failed and/or refused to complete the remaining five houses described above let alone execute the leases thereof to the plaintiffs and this, even though an appropriate draft lease covering the said five houses was duly presented by the plaintiffs to the defendants for execution.
Finally, paragraphs 13 and 14 of the plaintiff’s statement of claim state as follows:- “13. If the lease is not executed by the defendant the plaintiff says (as the fact is) that it will, owing to the defendant’s wrongful refusal and neglect to complete the houses and give possession thereof as with the time provided for by the agreement, have sustained damage to the extent of £5,000 made up of sums expended for or value of, temporary accommodation secured for its employees pending the completion of the said houses. 14. If the said lease is not executed the plaintiff says (as the fact is) that it will, owing to the defendants’ breach of contract have sustained damage to the extent of £12,750 made up of the difference between the rent payable under the said agreement for three years and the rent which the plaintiff will now have to pay for comparable houses today for a three year period at an annual rent of £2,750 per house.”
By their amended statement of defence, the defendants state that although there was negotiation between the parties concerning the leases of the houses in question, there was no binding agreement of the type postulated by the statement of claim. The defendants’ statement of defence further avers that they will rely on a number of letters specified in their statement of defence to prove that there was no binding agreement to let the houses concerned to the plaintiffs and that with respect to the amount of £2,500 (or N5,000) stated by the plaintiffs to have been deposited with the defendants, the statement of defence avers in paragraphs 6 and 7 as follows:- “6. The defendants aver that in the course of the negotiation pleaded in paragraph 4 hereof and at their (defendants’) request, the plaintiffs paid a sum of £2,500 through the estate agents to the defendants on the understanding:- (a) that the five houses will be completed on the dates specified in paragraph 6 of the statement of claim; (b) on failure by the defendants to complete the houses by the dates aforesaid the said sum of £2,500 or such proportion thereof as may be applicable, having regard to the number of houses completed, will be refundable to the plaintiff. 7. When the defendants, in fact, were unable to complete the houses on the dates referred to in paragraph 6 of the statement of claim, they returned the sum of £2,5000 to the plaintiffs through the estate agents and, in addition, they undertook to pay reasonable interest on the deposit aforesaid. The sum was paid on the 25th March, 1969, and received by the estate agents on the 26th March, 1969.” The statement of defence further avers that the deposit of £2,500 (or N5,000) was duly returned to the plaintiffs, that the land on which the houses were being erected was State land within the meaning of the state Land Act, Cap. 45, that the defendants’ title to the said land is subject to the provisions of Section 7 of that Act, that the houses were uncompleted at the date of the issue of the writ of summons, that there is no sufficient memorandum in writing of any agreement between the parties as required by law and that in any case if there was any such binding agreement, as the plaintiffs claimed, “the said plaintiffs have elected to waive any claim for specific performance and to treat any breach by the defendants of their obligation to complete the houses by specific dates as a discharge of such contract”.
As stated before, this appeal concerns two cases which were consolidated for hearing. In the other case, i.e. Suit No. LD/243/69, the plaintiffs are, as stated before, Jammal Engineering (Nigeria) Ltd., and they had sued as the defendants Shell BP Petroleum Development Co. of Nigeria Ltd. As plaintiffs in that case, Jammal Engineering (Nigeria) Ltd., averred in their statement of claim that they are indeed the owners of lands in the Jammal Estate, Ikoyi, registered under the Registration of Titles Act as No. L05091 and No. L05092 and that a Mr. Morgan and a Mr. Siddiqi of the plaintiffs’ company, without the authority of the company, purported to acknowledge on behalf of the company a tenancy agreement dated the 14th March, 1969, in respect of three houses situate on the said Jammal Estate, Ikoyi. Paragraphs 9, 10 and 11 of their pleadings are to the following effect:- “9. The said Tenancy Agreement dated 14th March, 1969, was not made by deed. 10. The defendants